 PDU'S 1 THROUGH 7, AND 23R ú  25-57-07
 ú ú 06 Page 505 ú Oct 18/00
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
747-400 MAINTENANCE MANUAL
 MASTER CARGO CONTROL PANEL - REMOVAL/INSTALLATION
_________________________________________________
 1.  General_______
 A.  The master cargo control panel is on the loadmaster control station on the left sidewall of the main deck, near the nose cargo door opening.
 TASK 25-57-08-004-001
 2.  Master Cargo Control Panel Removal (Fig. 401)__________________________________
 A.  Access
 (1)  Location Zone
 210 Main Deck

 B.  Procedure
 S 864-002
 (1)  Open the circuit breaker and attach DO-NOT-CLOSE tag:
 (a)  P415 Power Distribution Center Right Panel 1) 415F15 CARGO HANDLING CONT MAIN DECK
 S 034-003
 (2)  
Remove the fasteners on the master cargo control panel.

 S 034-004

 (3)  
Pull the master cargo control panel out until you see the electrical connector.

 S 034-005

 (4)  
Disconnect the electrical connector.

 S 024-006

 (5)  
Remove the panel.


 TASK 25-57-08-404-007
 3.  Master Cargo Control Panel (Fig. 401)__________________________
 A.  References
 (1)  24-22-00/201, Manual Control
 B.  Access
 (1)  Location Zone
 210 Main Deck

 C.  Procedure
 S 434-008
 (1)  Connect the electrical connector on the master cargo control panel.
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 25-57-08
 ALL  ú ú 03 Page 401 ú Oct 18/00
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A 747-400 MAINTENANCE MANUAL
 (2)  S 424-009Put the master cargo control panel in its position.
 (3)  S 434-010Install the fasteners to the master cargo control panel.
 (4)  S 864-012Remove the DO-NOT-CLOSE tag and close the circuit breaker: (a) P415 Power Distribution Center Right Panel 1) 415F15 CARGO HANDLING CONT MAIN DECK
 (5)  S 864-013Supply the electrical power (AMM 24-22-00/201).
 (6)  S 714-011To do a check of the master cargo control panel operation, do the steps that follow: (a) Push the system power ON switch on the master cargo control panel. (b) Make sure all the lights on the panel are on. (c) Push the system power STOP switch on the panel.
 (7)  S 864-014Remove the electrical power if it is not necessary (AMM 24-22-00/201).

 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 25-57-08
 ALL  ú ú 03 Page 402 ú Oct 18/00
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A

747-400
MAINTENANCE MANUAL

EQUIPMENT PANEL 
SEE  A  MASTER CARGO CONTROL PANEL 
SEE  B 
EQUIPMENT PANEL 

FASTENER 
(3 LOCATIONS) 

SCREW (4 LOCATIONS)
MASTER CARGO CONTROL PANEL BMaster Cargo Control Panel Installation Figure 401
C25407
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 25-57-08
 ALL  ú ú 01 Page 403 ú Feb 15/99
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
747-400 MAINTENANCE MANUAL
 SIDE DOOR MASTER CARGO CONTROL PANEL - REMOVAL/INSTALLATION
___________________________________________________________
 1.  General
_______
 A.  This procedure has these tasks:
 (1)  
The removal of the side door master cargo control panel.

 (2)  
The installation of the side door master cargo control panel.


 B.  The control panel is aft of the side cargo door and attaches to a lining on the sidewall.
 
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:747-400 AMM 飞机维护手册 EQUIPMENT/FURNISHINGS 2(90)