(f)
Remove the heat shrink tubing from the switch terminals.
(g)
Solder the switch terminals to release the wires from the switch.
(h)
Remove the switch.
TASK 22-11-39-404-006
3. Takeoff/Go-Around Switches Installation (Fig. 401)_______________________________________
A. Standard Tools and Equipment
(1)
Gun - Heat; Commercially available
(2)
Tool - Soldering; Commercially available
(3)
Tubing - Heat Shrinkable; RT-876; Raychem Corp., Redwood City, CA
B. References
(1) AMM 22-11-39/501, Takeoff/Go-Around Switch
C. Access
(1) Location Zones
101 Control Cabin Left
102 Control Cabin Right
D. Procedure
S 424-007
(1) Do these steps to install the switch:
(a)
Put the wire at each end of the switch through a heat shrink tubing.
(b)
Solder the wires to the new switch terminals.
(c)
Move the heat shrink tubing to all the terminals.
(d)
Blow the hot air on the heat shrink tubing to make it smaller.
(e)
Put the switch in the switch holder.
(f)
Install the washer and retaining nut.
(g)
Tighten the nut.
(h)
Install the switch and the switch holder into the switch housing.
(i)
Install the switch mounting screws.
(j)
Tighten the mounting screws.
(k)
Install the switch housing cover.
EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú
22-11-39
ALL ú ú 01 Page 403 ú Nov 15/93
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
737-300/400/500MAINTENANCE MANUAL
E. Takeoff/Go-Around Switches Test
S 864-008
(1) Close these circuit breakers and remove the DO-NOT-CLOSE tags:
(a)
P6 Circuit Breaker Panel
1) AUTO FLT CONT SYS B SNSR EXC AC
2) AUTO FLT CONT SYS B FCC DC
3) AUTO FLT CONT SYS B WARN LIGHT BAT
(b)
P18 Circuit Breaker Panel
1) AUTO FLT CONT SYS A SNSR EXC AC
2) AUTO FLT CONT SYS A FCC DC
3) AUTO FLT CONT SYS A WARN LIGHT BAT
4) AUTOTHROTTLE AC
5) AUTOTHROTTLE DC
S 714-009
(2) Do this task: "Takeoff/Go-Around Switch - Adjustment/Test" (AMM 22-11-39/501).
EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú
22-11-39
ALL ú ú 01 Page 404 ú Nov 15/93
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
737-300/400/500MAINTENANCE MANUAL
TAKEOFF/GO-AROUND SWITCH ADJUSTMENT/TEST
________________________________________
1. General_______
A. This procedure contains the installation test of the Takeoff/Go-Around switch (TOGA).
B. The Autothrottle Built-In Test Equipment is used to do the operational test after the installation of the Takeoff/Go-Around (TO/GA) switches. This test makes sure that the TO/GA switches operate correctly. It uses no external equipment. The airplane electrical and hydraulic systems are the only power sources necessary for this task.
C. You can find the TO/GA switches on the upper aft edge of each engine thrust lever.
TASK 22-11-39-715-001
2. Takeoff/Go-Around Switch Test_____________________________
A. References
(1)
22-31-00/501, Autothrottle
(2)
24-22-00/201, Manual Control
B. Access
(1) Location Zones
101 Control Cabin, Left
102 Control Cabin, Right
C. Takeoff/Go-Around Switch Test
S 745-002
(1)
Do the preparation for the Autothrottle BITE test in this task: "Operational Test - Autothrottle" (Ref 22-31-00/501).
S 745-003
(2)
Do a test on the TO/GA switch: