(1)
Prevent damage to the component interface and the adjacent area.
(2)
Make sure that the electrical connectors are clean and in the correct condition.
(3)
Do an inspection of the component interface and/or the adjacent area.
(4)
Lift the hot-cup holder (3).
(5)
Push the hot-cup (1) into the connector (2).
(6) Put the hot-cup holder (3) on the hot-cup (1). Subtask 25-35-25-865-052
B. Make sure that the related circuit breaker of the hot-cup at the related galley control panel is closed.
Subtask 25-35-25-861-051
C. Energize the aircraft electrical circuits
(Ref. TASK 24-41-00-861-002).
Subtask 25-35-25-710-050
D. Do the operational test of the hot-cup (Ref. TASK 25-35-00-710-020).
5. Close-up
________ Subtask 25-35-25-862-050
A. Close Access
(1)
Make sure that the work area is clean and clear of tool(s) and other items.
(2)
De-energize the aircraft electrical circuits
(Ref. TASK 24-41-00-862-002).
TASK 25-35-25-000-002 Removal of the Hot-Jug
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific 1 CAP - BLANKING
B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 25-35-25-991-002-A Fig. 402
3. Job Set-up
__________ Subtask 25-35-25-861-052
A. Energize the ground service network (Ref. TASK 24-42-00-861-001). Subtask 25-35-25-865-053
B. Preperation for the Removal of the Hot-Jug
(1) On the circuit breaker panel at the related galley:
(a) Open, safety and tag the related circuit breaker(s).
4. Procedure
_________ Subtask 25-35-25-020-051
A. Removal of the Hot-Jug
(Ref. Fig. 402/TASK 25-35-25-991-002-A)
(1)
Open the locks (2).
(2)
Carefully pull the hot-jug (3) out of the galley and remove the hot-jug (3) from the galley.
(3)
Put CAP - BLANKING on the disconnected electrical connectors.
Hot-Jug Figure 402/TASK 25-35-25-991-002-A
R EFF : 001-049, 101-105, 25-35-25 Page 407 May 01/05
CES
TASK 25-35-25-400-002 Installation of the Hot-Jug
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-41-00-861-002 Energize the Aircraft Electrical Circuits from the External Power 24-42-00-861-001 Energize the Ground Service Network from the External
Power 25-35-00-710-021 Operational Test of the Hot-Jug 25-35-25-991-002-A Fig. 402
3. Job Set-up
__________ Subtask 25-35-25-861-053
A. Energize the ground service network (Ref. TASK 24-42-00-861-001). Subtask 25-35-25-865-054
B. Preperation for the Installation of the Hot-Jug
(1) On the circuit breaker panel at the related galley:
(a) Open, safety and tag the related circuit breaker(s).
4. Procedure
_________ Subtask 25-35-25-420-051
A. Installation of the Hot-Jug
(Ref. Fig. 402/TASK 25-35-25-991-002-A)
(1)
Prevent damage to the component interface and the adjacent area.
(2)
Remove the blanking caps from the electrical connectors.
(3)
Do an inspection of the component interface and/or the adjacent area.
(4)
Make sure that the electrical connectors are clean and in the correct condition.
(5)
Carefully push the hot-jug (3) into the galley.
(6)
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM EQUIPMENT/FURNISHINGS 设备3(56)