(2)
Install the screws (6) and the washers (5). TORQUE the screws to between 1.2 and 2.0 m.daN (106.19 and 176.99 lbf.in).
(3)
Use the Feeler Gauges and measure the dimension B between the waste chute flap (1) and the wash basin, this must be to 1.0 mm (0.03 in.). If necessary, adjust as follows:
(a)
Loosen the screws (6) and adjust the waste chute flap (1) until you get dimension B.
(b)
TORQUE tighten the screws (6) to between 1.2 and 2.0 m.daN
(106.19 and 176.99 lbf.in).
(4)
Install the waste container (3) and close the access door (2).
(5) Push the waste chute flap (1) and make sure it operates correctly. **ON A/C ALL
5. Close-up
________
Subtask 25-45-15-862-050
A. De-energize the ground service network
(Ref. TASK 24-42-00-862-001).
EFF : ALL
25-45-15Page 407
ASH TRAY - REMOVAL/INSTALLATION
_______________________________
TASK 25-45-16-000-001 Removal of the Ash Tray
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 25-45-16-991-001 Fig. 401
3. Job Set-up
__________ Subtask 25-45-16-861-050
A. Aircraft Maintenance Configuration
(1) Energize the ground service network
(Ref. TASK 24-42-00-861-001).
4. Procedure
_________ Subtask 25-45-16-020-050
A. Removal of the Ash Tray
(Ref. Fig. 401/TASK 25-45-16-991-001)
(1)
Remove the ash tray (1) from the ash tray shell (2).
(2)
Remove the screws (3) and the ash tray shell (2) from the Lavatory wall.
EFF : ALL
25-45-16Page 401
R Ash Tray Figure 401/TASK 25-45-16-991-001
EFF : ALL 25-45-16 Page 402 Feb 01/05
CES
TASK 25-45-16-400-001 Installation of the Ash Tray
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 24-42-00-862-001 De-energize the Ground Service Network Supplied from the External Power 25-45-16-991-001 Fig. 401
3. Job Set-up
__________ Subtask 25-45-16-860-050
A. Aircraft Maintenance Configuration
(1) Make sure that the ground service network is energized
(Ref. TASK 24-42-00-861-001).
4. Procedure
_________ Subtask 25-45-16-210-050
A. Preparation for Installation
(1)
Clean the component interface and/or the adjacent area.
(2)
Make sure that the parts retained from the removed component are clean and in the correct condition.
(3)
Do an inspection of the component interface and/or the adjacent area.
EFF : ALL
25-45-16Page 403
Subtask 25-45-16-420-050
B. Installation of the Ash Tray
(Ref. Fig. 401/TASK 25-45-16-991-001)
(1)
Put the ash tray shell (2) in position on the lavatory wall.
(2)
Install the screws (3).
(3)
Install the ash tray (1) on the ash tray shell (2).
5. Close-up
________ Subtask 25-45-16-862-050
A. De-energize the ground service network
(Ref. TASK 24-42-00-862-001).
EFF : ALL
25-45-16Page 404
WASTE BOX - REMOVAL/INSTALLATION
________________________________
TASK 25-45-17-000-001 Removal of the Waste Box
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM EQUIPMENT/FURNISHINGS 设备3(118)