B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 29-00-00-864-001 Put the Related Hydraulic System in the Depressurized Configuration before Maintenance Action 52-41-00-010-001 Open the APU Doors for Access
3. Job Set-up
__________ Subtask 49-91-22-860-054
A. Aircraft Maintenance Configuration
(1)
Energize the ground service network
(Ref. TASK 24-42-00-861-001).
(2)
On the panel 25VU make sure that the APU MASTER SW p/bsw is OFF.
(3)
Make sure that there is a warning notice in the cockpit to tell persons not to start the APU.
(4)
Make sure that hydraulic systems are depressurized
(Ref. TASK 29-00-00-864-001).
Subtask 49-91-22-865-050
B. Open, safety and tag this(these) circuit breaker(s):
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------121VU APU/APU/CTL 2KD L42 121VU APU/ECB/SPLY 1KD L41
Subtask 49-91-22-010-050
C. Get Access
(1)
Put the access platform below the APU access doors 315AL and 316AR.
(2)
Open the access doors 315AL, 316AR (Ref. TASK 52-41-00-010-001).
(3)
Set the LIGHT SW 11LJ to the ON position.
4. Procedure
_________ Subtask 49-91-22-020-050
A. Removal of the Oil-Pump Differential-Pressure Indicator
(1)
Remove and discard the lockwire from the oil-pump
differential-pressure indicator (1).
(2)
Remove the differential pressure indicator (1) from the oil pump assembly (2).
(3)
Remove and discard the O-rings (3) and (4).
(4)
Put blanking plugs on the disconnected line ends.
TASK 49-91-22-400-001
Installation of the Oil-Pump Differential-Pressure Indicator (GTCP 36-300)
WARNING : DO NOT TOUCH THE APU UNTIL IT IS SUFFICIENTLY COOL TO PREVENT BURNS
_______ WHEN YOU DO THE MAINTENANCE TASK(S).
1. Reason for the Job
__________________
Self Explanatory
2. Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific access platform 3.5 m (11 ft. 6 in.) No specific Torque Wrench : range 0.20 to 3.60 m.daN
(2.00 to 26.00 lbf.ft)
B. Consumable Materials
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
Material No. 03-002 GB DEF-STAN 91-101
LUBRICATING OIL TURBINE ENGINE SYNT BASE
(Ref. 20-31-00) Material No. 19-010 USA AMS 5687
LOCKWIRE STAINLESS STEEL ANNEALED 0.8MM DIA
(Ref. 20-31-00)
C. Expendable Parts
-------------------------------------------------------------------------------FIG.ITEM |DESIGNATION |IPC-CSN -------------------------------------------------------------------------------
3 packing 49-91-45 01 -050 3 packing 49-91-45 01A-050 4 packing 49-91-45 01 -060 4 packing 49-91-45 01A-060
D. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 24-42-00-862-001 De-energize the Ground Service Network Supplied from the External Power 29-00-00-864-001 Put the Related Hydraulic System in the Depressurized Configuration before Maintenance Action 29-14-00-614-002 Pressurization of the Hydraulic Reservoirs through
the Ground Connector 49-00-00-860-003 APU Start by External Power (GTCP 36-300) 49-00-00-860-004 APU Shutdown by External Power (GTCP 36-300) 49-90-00-600-001 Check Oil Level and Replenish (GTCP 36-300) 52-41-00-010-001 Open the APU Doors for Access 52-41-00-410-001 Close the APU Doors after Access
3. Job Set-up
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM 机载辅助动力 AIRBORNE AUXILIARY POWER 6(93)