 Put the access platform in position below the APU access doors 315AL and 316AR.

 (2)
 Open the APU access doors 315AL, 316AR (Ref. TASK 52-41-00-010-001).

 (3)
 Set the LIGHT control switch 11LJ to the on position.

 


 4. Procedure
_________
 (Ref. Fig. 401/TASK 49-91-51-991-002) Subtask 49-91-51-020-052
 A. Removal of the Oil-Sump Temperatur Sensor
 (1)
 Disconnect the electrical connector (1) from the oil-sump temperature sensor (3).

 (2)
 Put blanking caps on the disconnected electrical connectors.

 (3)
 Put a container in position below the oil temperatur sensor.

 (4)
 Remove the bolt (2) and the oil-sump temperature sensor (3).

 (5)
 Install a blank plug in the oil sump.

 (6)
 Remove and discard the packing (4) from the oil-sump temperature sensor (3).

 


 Oil Temperature Sensor
 Figure 401/TASK 49-91-51-991-002

 CES  TASK 49-91-51-400-002 Installation of the Oil-Sump Temperature Sensor (8084KM) (APS 3200) WARNING : DO NOT TOUCH THE APU UNTIL IT IS SUFFICIENTLY COOL TO PREVENT BURNS


_______ WHEN YOU DO THE MAINTENANCE TASK(S).
 1.
 Reason for the Job

__________________
 Self Explanatory


 2.
 Job Set-up Information


______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific  Torque Wrench : range 5.00 to 35.00 lbf.in
 (0.05 to 0.40 m.daN)
 B. Consumable Materials
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
Material No. 04-012  USA VV-P-236 PURE MINERALVASELINE OR PETRO- LATUM (Ref. 20-31-00)
 C. Expendable Parts
 -------------------------------------------------------------------------------FIG.ITEM |DESIGNATION |IPC-CSN -------------------------------------------------------------------------------
packing  49-91-04 51A-030


 D. Referenced Information
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-41-00-861-002 Energize the Aircraft Electrical Circuits from the External Power 24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied from the External Power 29-00-00-864-001 Put the Related Hydraulic System in the Depressurized Configuration before Maintenance Action 29-14-00-614-002 Pressurization of the Hydraulic Reservoirs through
 the Ground Connector 49-00-00-710-008 Operational Test of the APU (APS 3200) 49-90-00-600-004 Check Oil Level and Replenish (APS 3200) 52-41-00-010-001 Open the APU Doors for Access 52-41-00-410-001 Close the APU Doors after Access 49-91-51-991-002 Fig. 401
 3. Job Set-up
__________
 Subtask 49-91-51-860-050
 A. Aircraft Maintenance Configuration
 (1)
 Make sure that the aircraft electrical circuits are energized (Ref. TASK 24-41-00-861-002).

 (2)
 On the panel 25VU, make sure that the APU MASTER SW pushbutton switch is off.

 (3)
 Make sure that there is a warning notice in the cockpit to tell persons not to start the APU.

 (4)
 Make sure that hydraulic systems are depressurized
 (Ref. TASK 29-00-00-864-001).


 (5)
 Make sure that the access platform is in position below the APU compartment.

 (6)
 Make sure that the APU access doors are open (Ref. TASK 52-41-00-010-001).

 (7)
 Make sure that the LIGHT control switch 11LJ is set to the on position.

 


 Subtask 49-91-51-865-056
 B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged
 -------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------121VU APU/APU/CTL 2KD L42 121VU APU/ECB/SPLY 1KD L41
 4. Procedure
_________
 (Ref. Fig. 401/TASK 49-91-51-991-002) Subtask 49-91-51-420-051
 A. Installation of the Oil-Sump Temperature Sensor
 (1)
 Apply COMMON GREASE (Material No. 04-012) to the new packing (4).

 (2)
 Install the new packing (4) on the oil-sump temperature sensor (3).
 