-------------------------------------------------------------------------------FIG.ITEM |DESIGNATION |IPC-CSN -------------------------------------------------------------------------------
O-ring 49-91-04 01 -020
D. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION
-------------------------------------------------------------------------------
49-00-00-710-004 Operational Test of the APU (4005KM) (GTCP 36-300)
49-90-00-600-001 Check Oil Level and Replenish (GTCP 36-300)
52-41-21-410-001
49-96-51-991-001 Fig. 401
3. Job Set-up
__________
Subtask 49-96-51-860-051
A. Aircraft Maintenance Configuration
(1)
Make sure that the warning notice is in position on the panel 25VU to tell persons not to start the APU.
(2)
Make sure that the access platform is in position below the APU access door 316AR.
(3)
Make sure that the access doors 315AL, 316AR are open.
Subtask 49-96-51-865-051
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------121VU APU/OIL/HTR/SPLY 1KT K41 121VU APU/APU/CTL 2KD L42 121VU APU/ECB/SPLY 1KD L41
4. Procedure
_________
(Ref. Fig. 401/TASK 49-96-51-991-001) Subtask 49-96-51-420-050
A. Installation of the APU Oil Heater
(1)
Make sure that the oil heater attachment pad is free from cracks and damage.
(2)
Remove the plastic blanking plug from the APU oil heater-flange on the accessory drive gearbox.
(3)
Clean the component interface and/or the adjacent area.
(4)
Do an inspection of the component interface and/or the adjacent area.
(5)
Lubricate the new O-ring (5) with OILS (Material No. 03-002) or OILS (Material No. 03-003).
(6)
Install the new O-ring (5) on the APU oil heater (4).
(7)
Put the APU oil heater (4) in position and install the washers (1) and the bolts (2).
(8)
TORQUE the bolts (2) to 50 lbf.in (0.56 m.daN).
(9)
Remove and discard the cable tie which temporarily holds the wiring harness connector (3) P28.
(10)
Remove the plastic blanking caps from the disconnected electrical connectors.
(a)
Make sure that the electrical connectors are clean and in the correct condition.
(b)
Connect the wiring harness connector (3) P28 to the APU oil heater (4).
(c)
Tighten the wiring harness connector (3) P28 with your hand. NOTE : Make sure that the color lock indicator is aligned.
(11)
Fill the APU oil reservoir (Ref. TASK 49-90-00-600-001).
(12)
Make sure that the work area is clean and clear of tool(s) and other items.
____ Subtask 49-96-51-865-052
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s): 1KD, 2KD, 1KT.
Subtask 49-96-51-790-050
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM 机载辅助动力 AIRBORNE AUXILIARY POWER 6(188)