 1.  General_______
 A.  This procedure has instructions to do the ground test for the air cooling pack system.
 TASK 21-51-00-745-001
 2.  Air Cooling Pack System Ground Tests____________________________________
 A.  General
 (1)  
The ground tests for the air cooling pack system includes the tests

 that follow: ~........................................... | <PTC-A/PACK-1 | <PTC-B/PACK-1 | ............................................. | <PTC-A/PACK-2 | <PTC-B/PACK-2 | ............................................. | <PTC-A/PACK-3 | <PTC-B/PACK-3 | ............................................. | <PTC-A/ALL PACKS | <PTC-B/ALL PACKS | 2.....................….....................1

 (2)  
The PTC-A/PACK-1, PTC-A/PACK-2, and PTC-A/PACK-3 ground tests do the tests for each pack with the pack temperature controller A. The PTC-A/ALL PACKS ground test does the test for all three packs with the pack temperature controller A.

 (3)  
The PTC-B/PACK-1, PTC-B/PACK-2, and PTC-B/PACK-3 ground tests do the tests for each pack with the pack temperature controller B. The PTC-B/ALL PACKS ground test does the test for all three packs with the pack temperature controller B.

 (4)  
Each ground test commands the applicable pack temperature controller and the applicable pack to do the conditions that follow:

 (a)  
The controller to do a self-test of its internal components.

 (b)  
Makes sure the controller has control of the applicable pack.

 (c)  
The flow control valve to close

 (d)  
The turbine bypass valve to move to the closed, half-open, and the fully open position

 (e)  
The ram air doors to move to the closed, half-open, and the fully open position.

 


 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 21-51-00
 ALL  ú ú 05 Page 501 ú Oct 10/96
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
 B.
C.
D.
A
747-400 MAINTENANCE MANUAL
 (f)  
The forward and aft cargo trim shutoff valves to open and close.

 (g)  
The forward and aft cabin shutoff valves to open and close.

 (h)  
The forward and aft cargo flow regulating valves to open and


 (5)
The test fails if one of the conditions does not occur.References

 (1)
24-22-00/201, Manual ControlAccess

 (1)  
Location Zone 221 Control Cabin, LH 222 Control Cabin, RH


Prepare for the Test
 S 865-002
 (1)  
Supply electrical power (Ref 24-22-00/201).

 S 865-007

 (2)  
Turn all the PACK selectors, on the overhead panel, P5, to the OFF position.

 S 865-013

 (3)  
To do the ground test for the pack temperature controller A, do the steps that follow:

 (a)  
Make sure this circuit breaker is open:

 1)  On the main power distribution panel, P6 a) 6F36, PACK TEMP CONT B

 (b)  
Make sure the PTC CHANNEL IN CONT, on the EICAS ECS maintenance page, shows A.

 


 S 865-012
 (4)  To do the ground test for the pack temperature controller B, do the steps that follow:
 (a)  
Make sure this circuit breaker is open:

 1)  On the main power distribution panel, P6 a) 6F35, PACK TEMP CONT A

 (b)  
Make sure the PTC CHANNEL IN CONT, on the EICAS ECS maintenance page, shows B.


 S 865-009
 (5)  Prepare the CDU for the test:
 (a)  
Push the MENU key on the CDU to show the MENU.

 (b)  
Push the line select key (LSK) that is adjacent to <CMC to show the CMC MENU.

 (c)  
If <RETURN shows after you push the LSK, push the LSK that is adjacent to <RETURN until you see the CMC MENU.

 (d)  
Push the LSK that is adjacent to <GROUND TESTS to show the GROUND TESTS menu.

 (e)  
Push the LSK adjacent to <21 AIR CONDITIONING to show the GROUND TESTS menu for the air conditioning system.