 S 024-117
 S 024-118
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 26-18-11
 ALL  ú ú 02 Page 408 ú Jul 15/95
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
737-300/400/500MAINTENANCE MANUAL
 S 984-052
 (22)
 In the area just fwd of the aft connection, turn the screw head on the support bracket 1/4 turn counterclockwise.

 S 024-120

 (23)
 Remove and save the white grommet.

 S 434-054

 (24)
 At the fwd connection, attach a piece of cord to the end connection. Make sure the piece of cord is long enough to span the length of the keel beam.

 S 984-055

 (25)
 At the aft end connection, pull the ovht detection element through the keel beam.

 S 024-121

 (26)
 Disconnect the cord from the ovht detection element, but allow it to remain inside of the keel beam.


 TASK 26-18-11-404-028
 5.  Aft Keel Beam Ovht Detection Element Installation (M273)________________________________________________________
 A. References
 (1)  
AMM 20-10-51/401, Flareless Tubing Assembly

 (2)  
AMM 29-09-00/201, Hydraulic Reservoir Pressurization System

 (3)  
AMM 32-31-71/401, Landing Gear Transfer Valve


 B. Installation
 S 424-029
 (1)  
At the aft connection location, attach the existing cord to the new M273 ovht detection element.

 S 984-057

 (2)  
Using two people, one at each end, slowly pull the cord fwd through the keel beam. Use the access holes in the bottom of the keel beam to help guide the ovht detection element through the holes in the structure.


 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 26-18-11
 ALL  ú ú 02 Page 409 ú Jul 15/95
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A 737-300/400/500MAINTENANCE MANUAL
 (3)  S 214-058Before attaching the element to the fwd and aft flange locations, make sure that the receptacles in the flanges are free of contaminants.
 (4)  S 424-122Attach the ovht detection element to the flange assemblies using the nut removed above. Torque the nut to 50-60 inch lbs.
 (5)  S 764-060Before the installation of the lockwire, make sure the electrical bond between the external surface of the element and structure is less than 0.010 ohms (SWPM 20-20-00). (a) If the resistance is greater than 0.010 ohms, disconnect the ovht detection element from the flange assemblies and clean the receptacle area. Repeat the previous steps.
 (6)  S 424-061Connect the electrical connectors to the fwd and aft connections of the ovht detection element.
 (7)  S 424-062Install lockwire per BAC5018 using the double twist method.
 (8)  S 424-063In the area just aft of the fwd connection, install a grommet around the ovht detection element.
 (9)  S 424-064Attach the grommet/element assembly to the bracket assembly by turning the screw head 1/4 turn clockwise.
 S 424-065

 (10) Through the access hole at BDY STA 690.4, install two (2) grommets on the ovht detection element.
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 26-18-11
 ALL  ú ú 02 Page 410 ú Nov 15/98
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A 737-300/400/500MAINTENANCE MANUAL
 S 424-066
 (11)
 Attach the grommet/element assembly to the brackets by turning the screw head 1/4 clockwise.

 S 424-067

 (12)
 Through the access hole at BDY STA 706.6, install a grommet on the ovht detection element.

 S 424-068

 (13)
 Attach the grommet/element assembly to the bracket by turning the screw head 1/4 turn clockwise.

 S 424-069

 (14)
 In the area just fwd of the aft connection, install a grommet on the ovht detection element.
 