 EDP PRESSURE SWITCH, AUTO SLAT SYSTEM
_____________________________________
 1.  General_______
 A.  There are two tasks in this procedure. There is a task for the removal and a task for the installation of the EDP pressure switch.
 TASK 29-22-41-004-001
 2.  EDP Pressure Switch Removal (Fig. 401)___________________________
 A.  Standard Tools and Equipment
 (1)  Container to catch hydraulic fluid
 B.  References
 (1)  
AMM 12-40-00/201, Cleaning and Washing

 (2)  
AMM 29-15-00/201, Hydraulic Systems A, B and Standby


 C.  Access
 (1)  Location Zone
 216 Main Wheel Well, RH

 D.  Prepare for Removal
 S 864-022
 (1)  
Remove power from hydraulic system B (AMM 29-15-00/201).

 S 864-023

 (2)  
Make sure these switches, on the P5 panel, are in the OFF position:

 (a)  
ELEC 1 HYD PUMPS B

 (b)  
FLT CONTROL B

 (c)  
ALTERNATE FLAPS

 


 E.  Remove the Pressure Switch
 S 034-014
 (1)  
Disconnect the electrical connector.

 (2)  
Disconnect the hydraulic line.

 (3)  
Drain hydraulic fluid into a container.

 S 164-017

 (4)  
Clean all hydraulic fluid from the installation area if it is necessary (AMM 12-40-00/201).

 (5)  
Remove the mounting bolts.


 S 034-015
 S 684-016
 S 034-018
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 29-22-41
 ALL  ú ú 01 Page 401 ú Nov 15/98
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A 737-300/400/500MAINTENANCE MANUAL
SEE  A 
RESERVOIR (REF) SYSTEM B 
SEE B SWITCH EDP PRESSURE 
MOUNTING BOLT WASHER (4 LOCATIONS)  A  SYSTEM B RETURN FILTER (REF) 
CLAMP 

HYDRAULIC LINE 
SWITCH EDP PRESSURE  ELECTRICAL CONNECTOR 
EDP PRESSURE SWITCH 

Figure 401 EDP Pressure Switch, Auto Slat System, Installation 

EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 29-22-41
 ALL  ú ú 01 Page 402 ú Nov 15/91
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
737-300/400/500MAINTENANCE MANUAL
 S 034-020
 (6)  
Remove the strap.

 S 024-019

 (7)  
Remove the EDP pressure switch.


 TASK 29-22-41-404-002
 3.  EDP Pressure Switch Installation (Fig. 401)________________________________
 A.  References
 (1)  
AMM 12-12-00/301, Hydraulic Reservoir

 (2)  
AMM 20-10-34/701, Metal Surfaces

 (3)  
SWPM 20-20-00, Standard Wiring Practices Manual

 (4)  
AMM 24-22-00/201, Manual Control

 (5)  
AMM 29-09-00/201, Hydraulic Reservoir Pressurization System

 (6)  
AMM 29-15-00/201, Hydraulic Systems A, B and Standby


 B.  Access
 (1)  Location Zone
 216 Main Wheel Well, RH

 C.  Procedure
 S 164-008
 (1)  
Clean the mounting surfaces (AMM 20-10-34/701).

 S 424-009

 (2)  
Install the EDP pressure switch.

 S 434-010

 (3)  
Install the mounting bolts.

 S 434-011

 (4)  
Connect the hydraulic line.

 S 284-021

 (5)  
Make sure the bond is 0.008 ohms maximum between the pressure switch and the mounting bracket (SWPM 20-20-00).

 (6)  
Connect the electrical connector.

 S 724-013

 (7)  
Do the functional test:

 (a)  
Pressurize the hydraulic reservoirs (AMM 29-09-00/201).

 (b)  
Supply electrical power (AMM 24-22-00/201).