 E.  Procedure
 S 867-001
 (1)  Open these circuit breakers and attach DO-NOT-CLOSE tags:
 (a)  
P6 Main Power Distribution Panel
 1) 6J32, FWD OVBD VLV CONT
 2) 6J33, ECS MISC PC ASSY


 (b)  
P180 DC Power Distribution Panel
 1) 180J20, FWD OVBD VALVE POWER

 

 S 027-002
 (2)  Remove the screen:
 (a)  
Get access to the screen in the space adjacent to the left side of the nose gear wheel well.

 (b)  
Loosen the clamp that holds the screen to the valve.

 (c)  
Remove the screen from the valve


 S 167-003
 (3)  Clean the screen:
 (a)  
Use the brush to clean the screen with soap and water.

 (b)  
Rinse the screen with water.

 (c)  
Dry the screen with the lint-free cloth and dry compressed air.


 S 427-004
 (4)  Install the screen:
 (a)  
Install the screen on the valve.

 (b)  
Tighten the clamp that holds the screen to the valve.


 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 21-26-15
 ALL  ú ú 01 Page 701 ú Feb 10/95
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A

747-400
MAINTENANCE MANUAL

FORWARD OVERBOARD VALVE
SEE A
SCREEN
CLAMP
VALVE
FWD
FORWARD OVERBOARD VALVE A
Screen Cleaning
Figure 701

A86372
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 21-26-15
 ALL  ú ú 01 Page 702 ú Oct 10/92
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
747-400 MAINTENANCE MANUAL
 S 867-005
 (5)  Remove the DO-NOT-CLOSE tags and close these circuit breakers:
 (a)  
P6 Main Power Distribution Panel
 1) 6J32, FWD OVBD VLV CONT
 2) 6J33, ECS MISC PC ASSY


 (b)  
P180 DC Power Distribution Panel
 1) 180J20, FWD OVBD VALVE POWER

 

 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 21-26-15
 ALL  ú ú 01 Page 703 ú Oct 10/92
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
747-400 MAINTENANCE MANUAL
 LOWER FORWARD CARGO OVERBOARD VALVE - REMOVAL/INSTALLATION
__________________________________________________________
 1.  General
_______
 A.  There are two tasks in this procedure. There is one task for the removal and one task for the installation of the lower forward cargo overboard valve.
 B.  The lower forward cargo overboard valve is installed in the floor area of the forward cargo compartment at station 770.
 TASK 21-26-17-004-001
 2.  Valve Removal (Fig. 401)
_____________
 A.  References
 (1)  
IPC 21-58-51 Fig. 10

 (2)  
SSM 21-23-02

 (3)  
WDM 21-23-22


 B.  Access
 (1)  Location Zone
 124 Forward Cargo Compartment Aft Half, RH

 C.  Procedure
 S 864-009
 (1)  Open these circuit breakers and attach DO-NOT-CLOSE tags:
 (a)  
P6 Main Power Distribution Panel
 1) 6E34 CARGO AIR COND PCA


 (b)  
P180 DC Power Distribution Panel
 1) 180E27 FWD CGO OVBD VLV PWR

 

 S 034-002
 (2)  Remove the electrical connector DV526 from the valve.
 NOTE: The valve is in the floor area of the forward cargo
____
 compartment at station 770.

 S 034-010
 (3)  
Remove the bonding jumper from the valve.

 (4)
Remove the clamp from each end of the valve and remove the valve.

 S 034-003
 