 D. Do the Installation Test of the Fan
 S 864-051
 (1)  
Supply electrical power (AMM 24-22-00/201).

 (2)  
Make sure the aft or the bulk cargo door is fully open.


 S 864-052
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 21-26-08
 ALL  ú ú 01F Page 404 ú Oct 10/93
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
747-400 MAINTENANCE MANUAL
 (3)  S 864-053Make sure the cargo air conditioning flow control switch on the overhead P461 panel is set to OFF.
 (4)  S 864-061Open, then close this circuit breaker on the main power distribution panel, P6: (a) E34, A/C CONT CARGO - PCA
 (5)  S 864-054Put the AFT CARGO VENT switch just forward of the cargo door to ON.
 (6)  S 714-055Make sure the fan operates. (a) Make sure air comes from the ceiling outlets.
 (7)  S 794-056Examine the area around the fan for air leaks. (a) Light leakage is permitted. (b) If the leakage is strong, align the joints and tighten the clamps.
 (8)  S 864-057Put the AFT CARGO VENT switch to OFF.
 (9)  S 404-058Install the sidewall lining (AMM 25-55-02/401).
 S 864-062

 (10)
 Close the aft or the bulk cargo door.

 S 864-059

 (11)
 Remove the electrical power, if it is not necessary. (AMM 24-22-00/201).


 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 21-26-08
 ALL  ú ú 01F Page 405 ú Oct 10/93
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
747-400 MAINTENANCE MANUAL
 BULK CARGO FLAPPER VALVE SOLENOID - MAINTENANCE PRACTICES
_________________________________________________________
 1.  General_______
 A.  This procedure has these tasks:
 (1)  
Remove the Bulk Cargo Flapper Valve Solenoid

 (2)  
Install the Bulk Cargo Flapper Valve Solenoid

 (3)  
Set the Position of the Bulk Cargo Flapper Valve


 B.  The flapper valve is on the left and right sidewall immediately forward of the aft bulkhead in the bulk cargo compartment. This procedure is for each flapper valve.
 C.  The flapper valve closes automatically during a test or an operation (discharge) of the cargo fire suppression system. This procedure gives instructions to open the flapper valve if the valve closes automatically.
 TASK 21-26-09-002-001
 2.  Remove the Bulk Cargo Flapper Valve Solenoid (Fig. 201)____________________________________________
 A.  References
 (1)  
24-22-00/201, Manual Control

 (2)  
25-55-02/401, Ceiling and Sidewall Lining

 (3)  
IPC 21-26-55 Fig. 2

 (4)  
WDM 21-28-31

 (5)  
SSM 21-28-03


 B.  Access
 (1)  Location Zones
 145 Bulk Cargo Compartment, Left
 146 Bulk Cargo Compartment, Right

 C.  Procedure
 S 862-002
 (1)  
Supply the electrical power (AMM 24-22-00/201).

 S 012-003

 (2)  
Remove the sidewall lining from the area around the flapper valve screen to get access to the valve solenoid (Ref 25-55-02/401).

 S 032-004

 (3)  
Remove the screws (4 locations) that hold the screen to the flapper valve and remove the screen.

 (4)
If the valve is open, set the valve to the closed position:


 S 822-005
 EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú

 21-26-09
 ALL  ú ú 02 Page 201 ú Jun 10/93
BOEING PROPRIETARY - Copyright (C) - Unpublished Work - See title page for details.
A
747-400
MAINTENANCE MANUAL


BULK CARGO FLAPPER VALVE


Bulk Cargo Flapper Valve Solenoid - Maintenance Practices
Figure 201 (Sheet 1)

EFFECTIVITYùùùùùùùùùùùùùùùùùùùùùùùùùùùùùù. ú
 
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:747-400 AMM 飞机维护手册 空调 AIR CONDITIONING 1(64)