A. Get Access
(1) Remove the oxygen storage cylinder (5750HM) (Ref. TASK 35-11-41-000-001)
4. Procedure
_________
Subtask 35-11-41-750-051
A. Hydrostatic test
(1) Do the hydrostatic test (Ref. CMM 351142)
EFF : ALL
35-11-41Page 601
5. Close-up
________ Subtask 35-11-41-420-052
A. Close Access
(1) Install the oxygen storage cylinder (5750HM) (Ref. TASK 35-11-41-400-001)
EFF : ALL
35-11-41Page 602
FILL PORT - OXYGEN (5769HM) - REMOVAL/INSTALLATION
__________________________________________________
TASK 35-11-42-000-001 Removal of the Oxygen Fill Port (5769HM) WARNING : KEEP ALL HYDROCARBONS (FUELS, LUBRICANTS, ETC.) AWAY FROM ALL SOURCE
_______ OF OXYGEN. OXYGEN BECOMES EXPLOSIVE WHEN IT TOUCHES HYDROCARBONS.
WARNING : CLEAN THE TOOLS AND MAKE SURE YOUR HANDS ARE CLEAN TO PREVENT
_______ CONTAMINATION OF THE OXYGEN SYSTEM.
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific blanking cap
No specific access platform 2 m (6 ft. 7 in.)
B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 35-11-42-991-001 Fig. 401
3. Job Set-up
__________ Subtask 35-11-42-861-050
A. Aircraft Maintenance Configuration
(1) Energize the ground service network (Ref. TASK 24-42-00-861-001).
Subtask 35-11-42-010-051
B. Get Access
(1)
Put an access platform in position at the access door 812.
(2)
Open the access door 812.
(3)
Close the valve of the cylinder (5750HM).
4. Procedure
_________
(Ref. Fig. 401/TASK 35-11-42-991-001) Subtask 35-11-42-020-053
A. Removal of the Oxygen Fill Port (5769HM)
(1)
Disconnect the tube (5) and discard the sleeve (4).
(2)
Put a blanking cap on the disconnected end of the tube (5).
(3)
Remove the nuts (3) and the screws (1).
(4)
Remove the fill port (2).
Oxygen Fill Port
Figure 401/TASK 35-11-42-991-001
EFF : 051-099, 35-11-42 Page 403
May 01/05
CES
TASK 35-11-42-400-001
Installation of the Oxygen Fill Port (5769HM)
1. Reason for the Job
__________________
Self Explanatory
2. Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific access platform 2 m (6 ft. 7 in.)
B. Consumable Materials
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
Material No. 05-003B USA MIL-G-27617 OXYGEN SYSTEM LUBRICANT (Ref. 20-31-00)
C. Expendable Parts
-------------------------------------------------------------------------------FIG.ITEM |DESIGNATION |IPC-CSN -------------------------------------------------------------------------------
sleeve 35-11-01 02A-020
D. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 35-11-42-991-001 Fig. 401