(4)
Install a serviceable escape-slide enclosure (Ref. TASK 25-62-47-400-001).
(5)
Install a serviceable inflation reservoir (Ref. TASK 25-62-49-400-001).
(6)
Make sure that the work area is clean and clear of tool(s) and other items.
(7)
Remove the warning notice(s).
(8)
Remove the safety barriers.
(9)
Remove the plastic sheet from the ground.
(10)
Remove the tacky tape and protection from the fuselage.
(11)
Remove the access platform(s).
EFF : 301-399, 25-62-00Page 525
Aug 01/04
R
CES
(12) Remove the ground support and maintenance equipment, the special and
standard tools and all other items.
R **ON A/C ALL
R TASK 25-62-00-780-001
R Gage System Test
R 1. Reason for the Job__________________
R Self Explanatory
R 2. Job Set-up Information______________________
R A. Referenced Information
R -------------------------------------------------------------------------------
R REFERENCE DESIGNATION
R -------------------------------------------------------------------------------
R 25-62-44-000-002 Removal of the Escape-Slide Pack-Assembly
R 25-62-44-400-001 Installation of the Escape-Slide Pack-Assembly
R CMM 25-65-17
R 3. Job Set-up__________
R Subtask 25-62-00-010-074
R A. Remove the Escape-Slide Pack-Assembly (Ref. TASK 25-62-44-000-002).
R 4. Procedure_________
R Subtask 25-62-00-780-050
R A. Do the pressure test of the gage system (Ref. CMM 25-65-17).
R 5. Close-up________
R Subtask 25-62-00-410-068
R A. Install the Escape-Slide Pack-Assembly (Ref. TASK 25-62-44-400-001).
EFF : ALL
25-62-00Page 527
Feb 01/05
ESCAPE FACILITIES - CABIN - INSPECTION/CHECK____________________________________________
TASK 25-62-00-210-001
Check Pressure at Door Escape-Slide/Slide Raft Pressure Gage (if not connected to CIDS)
1. Reason for the Job__________________
Refer to the MPD TASK: 256241-01
2. Job Set-up Information______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific FOR FIN 7506MM No specific access platform 2.0 m (6 ft. 7 in.)inspection mirror
B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
R R R R R R R 24-42-00-861-001 24-42-00-862-001 25-62-44-000-002 25-62-44-400-001 25-62-46-000-001 25-62-46-400-001 25-62-49-000-001 25-62-49-400-001 52-30-00-860-001 52-30-00-860-002 Energize the Ground Service Network from the External PowerDe-energize the Ground Service Network Supplied from the External Power Removal of the Escape-Slide Pack-Assembly Installation of the Escape-Slide Pack-Assembly Inflation Reservoir, Offwing Escape-Slide - Removal Inflation Reservoir, Offwing Escape-Slide -Installation Inflation Reservoir, Escape-Slide - Removal Inflation Reservoir, Escape-Slide - InstallationOpen the FWD or AFT Cargo-Compartment Door with the Yellow Electric PumpClose the FWD or AFT Cargo-Compartment Door with the Yellow Electric Pump
EFF : ALL
25-62-00Page 601
May 01/04
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 401-499,
25-62-00-991-001 **ON A/C 301-399,
25-62-00-991-001-A **ON A/C ALL
3. Job Set-up
__________
Fig. 601
Fig. 601A
Subtask 25-62-00-861-056
A. Energize the ground service network (Ref. TASK 24-42-00-861-001).
R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 401-499,
Subtask 25-62-00-010-061
B. Access to the Inflation Reservoir (1) (Ref. Fig. 601/TASK 25-62-00-991-001)
(1) Open the AFT cargo-compartment door (Ref. TASK 52-30-00-860-001).
(2) Put an access platform in position adjacent to the AFT cargo-compartment exit.