(b)
Install the screws (14) and the nuts (16).
(5)
Install the tie-down fitting (18):
(a)
Put the tie-down fitting (18) in position at the structure (3).
(b)
Install the screws (17) and the nuts (19).
(6)
Install the tie-down fitting (21):
(a)
Put the tie-down fitting (21) in position at the structure (3).
(b)
Install the screws (20) and the nuts (22).
(7)
Install the tie-down fitting (24):
(a)
Put the tie-down fitting (24) in position at the structure (3).
(b)
Install the screws (23) and the nuts (25).
(8)
Install the tie-down fittings (27): NOTE : The installation procedure for all the tie-down fittings (27)
____ is the same. Therefore, the installation procedure for one tie-down fitting (27) only is given here.
R EFF : 062-099, 106-149, 151-199, 203-299, 25-55-41Page 448 401-499, Aug 01/05
CES
(a)
Put the tie-down fitting (27) in position at the structure (3).
(b)
Install the screws (26) and the nuts (28).
(9) Install the tie-down fittings (30): NOTE : The installation procedure for all the tie-down fittings (30)
____ is the same. Therefore, the installation procedure for one tie-down fitting (30) only is given here.
(a)
Put the tie-down fitting (30) in position at the structure (3).
(b)
Install the screws (29) and the nuts (31).
(10)
Install the tie-down fitting (33):
(a)
Put the tie-down fitting (33) in position at the structure (3).
(b)
Install the screws (32) and the nuts (34).
(11)
Install the tie-down fitting (36):
(a)
Put the tie-down fitting (36) in position at the structure (3).
(b)
Install the screws (35) and the nuts (37).
(12)
Install the cargo net(s) (5), if removed:
(a)
Put the cargo net(s) (5) in position at the applicable net attachment fittings of the cargo-compartment floor and ceiling areas.
(b)
Connect the net fittings (6) to the net attachment fittings.
R EFF : 062-099, 106-149, 151-199, 203-299, 25-55-41Page 449 401-499, Aug 01/05
CES
**ON A/C 301-399,
Subtask 25-55-41-420-050-B
B. Installation of the Tie-Down and Net Attachment Fittings in the Floor Area of the AFT Cargo-Compartment (Ref. Fig. 401B/TASK 25-55-41-991-001-B)
(1) Install the tie-down points (2): NOTE : The installation procedure for all the tie-down points (2) is
____ the same. Therefore, the installation procedure for one tie-down point (2) only is given here.
(a)
Put the tie-down point (2) in position at the structure (3).
(b)
Install the screws (1) and the nuts (4).
(2) Install the tie-down points (8): NOTE : The installation procedure for all the tie-down points (8) is
____ the same. Therefore, the installation procedure for one tie-down point (8) only is given here.
(a)
Put the plug housing (9) in position at the structure (3), if removed.
(b)
Put the tie-down point (8) in position at the plug housing (9).
(c)
Install the screws (7) and the nuts (10).
(3) Install the tie-down fittings (12): NOTE : The installation procedure for all the tie-down fittings (12)
____ is the same. Therefore, the installation procedure for one tie-down fitting (12) only is given here.
(a)
Put the tie-down fitting (12) in position at the structure (3).
(b)
Install the screws (11) and the nuts (13).
(4) Install the tie-down fittings (15): NOTE : The installation procedure for all the tie-down fittings (15)
____ is the same. Therefore, the installation procedure for one tie-down fitting (15) only is given here.
(a)
Put the tie-down fitting (15) in position at the structure (3).
(b)
Install the screws (14) and the nuts (16).
(5) Install the tie-down fittings (18): NOTE : The installation procedure for all the tie-down fittings (18)
____ is the same. Therefore, the installation procedure for one tie-down fitting (18) only is given here.
(a)
Put the tie-down fitting (18) in position at the structure (3).
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM EQUIPMENT/FURNISHINGS 设备4(51)