 Put the plug housing (9) in position at the structure (3), if removed.

 (b)
 Put the tie-down point (8) in position at the plug housing (9).

 (c)
 Install the screws (7) and the nuts (10).


 (3) Install the tie-down fittings (12): NOTE : The installation procedure for all the tie-down fittings (12)
____ is the same. Therefore, the installation procedure for one tie-down fitting (12) only is given here.
 (a)
 Put the tie-down fitting (12) in position at the structure (3).

 (b)
 Install the screws (11) and the nuts (13).


 (4) Install the seat-track sections (15): NOTE : The installation procedure for all the seat-track sections
____ (15) is the same. Therefore, the installation procedure for one seat-track section (15) only is given here.


 (a)
 Put the seat-track section (15) in position at the structure (3).

 (b)
 Install the screws (14) and the nuts (16).


 (5)
 Install the tie-down fitting (18):

 (a)
 Put the tie-down fitting (18) in position at the structure (3).

 (b)
 Install the screws (17) and the nuts (19).

 

 (6)
 Install the tie-down fittings (21): NOTE : The installation procedure for all the tie-down fittings (21)


____ is the same. Therefore, the installation procedure for one tie-down fitting (21) only is given here.
 (a)
 Put the tie-down fitting (21) in position at the structure (3).

 (b)
 Install the screws (20) and the nuts (22).


 (7)
 Install the tie-down fitting (24):

 (a)
 Put the tie-down fitting (24) in position at the structure (3).

 (b)
 Install the screws (23) and the nuts (25).

 

 (8)
 Install the tie-down fitting (27):

 (a)
 Put the tie-down fitting (27) in position at the structure (3).

 (b)
 Install the screws (26) and the nuts (28).

 

 (9)
 Install the cargo net(s) (5), if removed:

 (a)
 Put the cargo net(s) (5) in position at the applicable net attachment fittings of the cargo-compartment floor and ceiling areas.

 (b)
 Connect the net fittings (6) to the net attachment fittings.

 (c)
 Install the screws (7) and the nuts (10).

 

 (3)
 Install the tie-down fittings (12): NOTE : The installation procedure for all the tie-down fittings (12)

 


R  **ON A/C 151-199, 201-202, 301-399, 401-499,
 Subtask 25-55-41-420-052-A
 D. Installation of the Tie-Down and Net Attachment Fittings in the Floor Area of the BULK Cargo-Compartment
 **ON A/C 151-199,
 (Ref. Fig. 403A/TASK 25-55-41-991-003-B)
 **ON A/C 201-202, 301-399,
 (Ref. Fig. 403B/TASK 25-55-41-991-003-A) 
R  **ON A/C 401-499, 
R  (Ref. Fig. 403C/TASK 25-55-41-991-003-C) 
R  **ON A/C 151-199, 201-202, 301-399, 401-499,
 (1) Install the tie-down points (2):
 NOTE : The installation procedure for all the tie-down points (2) is____ the same. Therefore, the installation procedure for one tie-down point (2) only is given here.
 (a) Put the tie-down point (2) in position at the structure (3).
 (b) Install the screws (1) and the nuts (4).
 (2) Install the tie-down points (8):
 NOTE : The installation procedure for all the tie-down points (8) is____ the same. Therefore, the installation procedure for one tie-down point (8) only is given here.
 (a) Put the plug housing (9) in position at the structure (3), if removed.
 (b) Put the tie-down point (8) in position at the plug housing (9). 

 

____ is the same. Therefore, the installation procedure for one tie-down fitting (12) only is given here.
 (a)
 Put the tie-down fitting (12) in position at the structure (3).

 (b)
 Install the screws (11) and the nuts (13).


 (4) Install the cargo net(s) (5), if removed:
 (a) Put the cargo net(s) (5) in position at the applicable net attachment fittings of the cargo-compartment floor and ceiling areas.
 (b) Connect the net fittings (6) to the net attachment fittings. **ON A/C 001-049, 051-099, 101-149, 221-221, 224-224, 228-228,
 Subtask 25-55-41-420-053
 E. Installation of the Tie-Down and Net Attachment Fittings in the Ceiling Area of the BULK Cargo-Compartment (Ref. Fig. 404/TASK 25-55-41-991-004)
 (1) Install the tie-down points (3): NOTE : The installation procedure for all the tie-down points (3) is
 