(b)
Install the screws (17) and the nuts (19).
(6) Install the seat-track sections (21): NOTE : The installation procedure for all the seat-track sections
____ (21) is the same. Therefore, the installation procedure for one seat-track section (21) only is given here.
(a)
Put the seat-track section (21) in position at the structure (3).
(b)
Install the screws (20) and the nuts (22).
(7)
Install the tie-down fitting (24):
(a)
Put the tie-down fitting (24) in position at the structure (3).
(b)
Install the screws (23) and the nuts (25).
(8)
Install the tie-down fittings (27): NOTE : The installation procedure for all the tie-down fittings (27)
____ is the same. Therefore, the installation procedure for one tie-down fitting (27) only is given here.
(a)
Put the tie-down fitting (27) in position at the structure (3).
(b)
Install the screws (26) and the nuts (28).
(9) Install the tie-down fitting (30):
(a)
Put the tie-down fitting (30) in position at the structure (3).
(b)
Install the screws (29) and the nuts (31).
(10)
Install the tie-down fitting (33):
(a)
Put the tie-down fitting (33) in position at the structure (3).
(b)
Install the screws (32) and the nuts (34).
(11)
Install the cargo net(s) (5), if removed:
(a) Put the cargo net(s) (5) in position at the applicable net attachment fittings of the cargo-compartment floor and ceiling areas.
(b) Connect the net fittings (6) to the net attachment fittings. **ON A/C ALL
Subtask 25-55-41-420-051
C. Installation of the Tie-Down and Net Attachment Fittings in the Ceiling Area of the AFT Cargo-Compartment
**ON A/C 001-049, 051-099, 101-149, 201-299,
(Ref. Fig. 402/TASK 25-55-41-991-002) R **ON A/C 151-199, 401-499,
(Ref. Fig. 402A/TASK 25-55-41-991-002-A)
**ON A/C 301-399,
(Ref. Fig. 402B/TASK 25-55-41-991-002-B)
**ON A/C ALL
(1) Install the tie-down points (3): NOTE : The installation procedure for all the tie-down points (3) is
____ the same. Therefore, the installation procedure for one tie-down point (3) only is given here.
EFF : ALL
25-55-41Page 452
(a) Install the spacer (2), if removed: 1 Put the spacer (2) in position at the structure (1).
_
2 Install the screws (5) in the spacer (2).
_
(b)
Put the tie-down point (3) in position at the spacer (2).
(c)
Install the screws (4) in the tie-down point (3).
(2) Install the tie-down points (6): NOTE : The installation procedure for all the tie-down points (6) is
____ the same. Therefore, the installation procedure for one tie-down point (6) only is given here.
(a)
Put the tie-down point (6) in position at the structure (1).
(b)
Install the screws (7) in the tie-down point (6).
(3)
Install the stanchion fitting (10):
(a)
Put the stanchion fitting (10) in position at the structure (1).
(b)
Install the screws (11) in the stanchion fitting (10).
(4)
Install the cargo net(s) (9), if removed:
(a) Put the cargo net(s) (9) in position at the applicable net attachment fittings of the cargo-compartment floor and ceiling areas.
(b) Connect the net fittings (8) to the net attachment fittings. **ON A/C 001-049, 051-099, 101-149, 203-299,
Subtask 25-55-41-420-052
D. Installation of the Tie-Down and Net Attachment Fittings in the Floor Area of the BULK Cargo-Compartment
**ON A/C 001-049, 051-099, 101-149, 221-221, 224-224, 228-228,
(Ref. Fig. 403/TASK 25-55-41-991-003) **ON A/C 203-220, 222-223, 225-227, 229-299,
(Ref. Fig. 403B/TASK 25-55-41-991-003-A) **ON A/C 001-049, 051-099, 101-149, 203-299,
(1) Install the tie-down points (2): NOTE : The installation procedure for all the tie-down points (2) is
____ the same. Therefore, the installation procedure for one tie-down point (2) only is given here.
(a)
Put the tie-down point (2) in position at the structure (3).
(b)
Install the screws (1) and the nuts (4).
(2) Install the tie-down points (8): NOTE : The installation procedure for all the tie-down points (8) is
____ the same. Therefore, the installation procedure for one tie-down point (8) only is given here.