The electrical connector (8), or the progamming-dongle (19) (if installed).
-
The RCP connector (12).
(b)
Use CLEANING AGENTS (Material No. 11-004) with a MISCELLANEOUS (Material No. 19-003) and clean:
-
The electrical connector (8), or the programming-dongle (19) (if installed).
-
The RCP connector (12).
(c)
Make sure that they are dry before you continue.
(2)
Do an inspection of the component interface and/or the adjacent area.
(3)
Make sure that the ON/OFF/ARM switch (10) is set to the OFF position.
(4)
Install the ELT (5):
(a) Carefully hold the ELT (5) and the auxiliary-antenna (4) in position on the bracket (1).
NOTE : Be careful with the auxiliary-antenna (4), it is attached
____
to the ELT (5) with the safety strap (17).
(b)
Bend the auxiliary-antenna (4) back on itself, and push it through the loops (25) on the straps (3).
(c)
Push the straps (3) through the buckles (2).
(d)
Pull the straps (3) tight and fasten the burr-strips.
(5)
Remove the blanking caps from the electrical connectors.
(6)
Make sure that the electrical connectors are clean and in the correct condition.
(7)
Connect the electrical connector (8), or the programming-dongle (19) (if installed) to the RCP connector (12).
(8)
Connect the antenna connector (9) to the ANT connection (11).
(9)
Safety the connection between the electrical connector (8), or the programming-dongle (19) (if installed), to the RCP connector (12).
WARNING : OBEY THE MANUFACTURER'S INSTRUCTIONS WHEN YOU USE
_______ THIS/THESE MATERIAL/S. USE PROTECTIVE CLOTHING, RUBBER GLOVES AND GOGGLES.
(a) Apply PAINTS FOR DETAIL (INTERNAL AND EXTERN AL) (Material No. 07-020) (14) to the connection.
(10) Set the ON/OFF/ARM switch (10) to the ARM position. Subtask 25-65-35-740-050
C. Do the BITE test (Ref. TASK 25-65-00-740-001).
5. Close-up
________ Subtask 25-65-35-410-050
A. Close Access
(1)
Make sure that the work area is clean and clear of tool(s) and other items.
(2)
Install the ceiling panel 261BC (Ref. TASK 25-23-42-400-002).
(3)
Remove the ground support and maintenance equipment, the special and standard tools and all other items.
Subtask 25-65-35-862-050
B. De-energize the ground service network (Ref. TASK 24-42-00-862-001). STRAP - SAFETY BARRIER - REMOVAL/INSTALLATION
_____________________________________________
TASK 25-65-41-000-001
Safety Barrier Strap - Removal
NOTE : The procedures are given for the removal of a safety barrier strap from
____ one door; the procedures for the removal of the safety barrier straps from all doors (left and right) are almost the same.
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------
REFERENCE QTY DESIGNATION
-------------------------------------------------------------------------------
No specific access platform 3.4 m (11 ft. 2 in.)
B. Referenced Information
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
25-80-00-000-001 Removal of the Insulation Blankets
52-10-00-010-001 Opening of the Passenger/Crew Door
R 52-22-00-010-001 Opening of the Emergency Exit Doors from the
R Passenger Compartment
R 52-22-00-010-002 Opening of the Emergency Exit Doors from the Outside
25-65-41-991-001 Fig. 401
EFF : ALL
25-65-41Page 401
3. Job Set-up
__________ R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 401-499,
Subtask 25-65-41-010-050
A. Get Access
(1)
Put the access platform adjacent to the passenger/crew door you will work from.
(2)
Open the passenger/crew door (Ref. TASK 52-10-00-010-001).