(a)
Put the tie-down fitting (14) in position at the structure (3).
(b)
Install the screws (13) in the tie-down fitting (14).
(6)
Install the tie-down fittings (16): NOTE : The installation procedure for all the tie-down fittings (16)
____ is the same. Therefore, the installation procedure for one tie-down fitting (16) only is given here.
(a)
Put the tie-down fitting (16) in position at the structure (3).
(b)
Install the screws (15) in the tie-down fitting (16).
(7) Install the cargo net(s) (6), if removed:
(a) Put the cargo net(s) (6) in position at the applicable net attachment fittings of the cargo-compartment floor and ceiling areas.
(b) Connect the net fittings (7) to the net attachment fittings. R **ON A/C 151-199, 401-499,
Subtask 25-54-41-420-050-A
B. Installation of the Tie-Down and Net Attachment Fittings in the Floor Area (Ref. Fig. 401A/TASK 25-54-41-991-001-A)
(1) Install the tie-down points (4): NOTE : The installation procedure for all the tie-down points (4) is
____ the same. Therefore, the installation procedure for one tie-down point (4) only is given here.
(a)
If removed, put the plug housing (5) in position at the structure (6).
(b)
Put the tie-down point (4) in position at the plug housing (5).
(c)
Install the screws (3) in the tie-down point (4).
R EFF : 001-049, 051-099, 101-149, 151-199, 25-54-41Page 420 201-299, 401-499, Aug 01/05
CES
(2) Install the tie-down points (8): NOTE : The installation procedure for all the tie-down points (8) is
____ the same. Therefore, the installation procedure for one tie-down point (8) only is given here.
(a)
Put the tie-down point (8) in position at the structure (6).
(b)
Install the screws (7) in the tie-down point (8).
(3)
Install the seat-track section (10):
(a)
Put the seat-track section (10) in position at the structure (6).
(b)
Install the screws (9) in the seat-track section (10).
(4)
Install the tie-down fitting (12):
(a)
Put the tie-down fitting (12) in position at the structure (6).
(b)
Install the screws (11) in the tie-down fitting (12).
(5)
Install the tie-down fittings (14): NOTE : The installation procedure for all the tie-down fittings (14)
____ is the same. Therefore, the installation procedure for one tie-down fitting (14) only is given here.
(a)
Put the tie-down fitting (14) in position at the structure (6).
(b)
Install the screws (13) in the tie-down fitting (14).
(6) Install the tie-down fittings (16): NOTE : The installation procedure for all the tie-down fittings (16)
____ is the same. Therefore, the installation procedure for one tie-down fitting (16) only is given here.
(a)
Put the tie-down fitting (16) in position at the structure (6).
(b)
Install the screws (15) in the tie-down fitting (16).
(7) Install the cargo net(s) (1), if removed:
(a)
Put the cargo net(s) (1) in position at the applicable net attachment fittings of the cargo-compartment floor and ceiling areas.
(b)
Connect the net fittings (2) to the net attachment fittings.
**ON A/C 301-399,
Subtask 25-54-41-420-050-B
B. Installation of the Tie-Down and Net Attachment Fittings in the Floor Area (Ref. Fig. 401B/TASK 25-54-41-991-001-B)
(1) Install the tie-down points (2): NOTE : The installation procedure for all the tie-down points (2) is
____ the same. Therefore, the installation procedure for one tie-down point (2) only is given here.
(a)
Put the tie-down point (2) in position at the structure (3).
(b)
For the tie-down points (2) installed between FR35 and FR35.4: 1 Install the screws (1) and the nuts (4).
_
(c)
For the tie-down points (2) installed at all other frame positions:
1 Install the screws (1) in the tie-down point (2).
_
(2)
Install the seat-track section (6):
(a)
Put the seat-track section (6) in position at the structure (3).
(b)
Install the screws (5) in the seat-track section (6).
(3)
Install the tie-down points (10): NOTE : The installation procedure for all the tie-down points (10) is
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM EQUIPMENT/FURNISHINGS 设备4(15)