R Supplemental Life Raft/s - Component Location Figure 401B/TASK 25-66-41-991-002-B
R EFF : 301-301, 303-399, 25-66-41 Page 405 May 01/05
CES
5. Close-up
________ Subtask 25-66-41-410-050
A. Close Access
(1)
Install serviceable/replacement supplemental life raft(s) and if necessary, attach/close the strap/clamp.
(2)
Close the door/access panel of the stowage compartment(s).
(3)
Make sure that the work area is clean and clear of tool(s) and other items.
Subtask 25-66-41-862-051
B. De-energize the ground service network
(Ref. TASK 24-42-00-862-001).
LIFE VEST - REMOVAL/INSTALLATION
________________________________
TASK 25-66-52-920-001
Remove Life Vests for Restoration
1.
Reason for the Job
__________________
Refer to the MPD TASK: 256652-01
2.
Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 24-42-00-862-001 De-energize the Ground Service Network Supplied from the External Power R
3. Job Set-up
__________
Subtask 25-66-52-861-050
A. Energize the ground service network
(Ref. TASK 24-42-00-861-001).
Subtask 25-66-52-010-050
B. Get Access
(1)
Get access to all life vests found at these locations:
-Below the passenger seats.
-In the cabin attendant seat (CAS).
-Behind the flight crew seats.
-In stowage compartments identified with placards.
(2)
Remove all life vests from the aircraft for restoration.
EFF : ALL
25-66-52Page 401
4. Procedure_________
R Subtask 25-66-52-280-050
R A. Workshop Procedure
R R (1) Do the restoration of the life vests. Refer to the applicable Component Maintenance Manuals (CMM) for the correct procedure.
5. Close-up________
Subtask 25-66-52-410-050
A. Close Access
(1) Install serviceable/replacement life vests at these locations: - Below the passenger seats. - In the CAS's. - Behind the flight crew seats. - In stowage compartments identified with placards.
Subtask 25-66-52-862-050
B. De-energize the ground service network (Ref. TASK 24-42-00-862-001).
EFF : ALL
25-66-52Page 402
SUPPLEMENTARY MEDICAL EQUIPMENT - DESCRIPTION AND OPERATION___________________________________________________________
1. General_______
2. Component Location__________________
3. System Description__________________
4. Power Supply____________
R **ON A/C 301-399,
A. 2001VU Panel The busbar 210XP supplies 115 VAC, 400Hz 1-phase to the socket 40MF, and is protected by the circuit breaker 7MF. The busbar 208PP supplies 28 VDC 1-phase to the socket 42MF, and is protected by the circuit breaker 6MF.
R B. Not Applicable
R **ON A/C 401-499,
R R R R R R A. Medical Outlets 40MF and 42MF The busbar 210XP supplies 115 VAC 400 Hz 1-phase to the socket 40MF, and is protected by the circuit breaker 7MF. The busbar 208PP supplies 28 V DC, 1-phase to the socket 42MF, and is protected by the circuit breaker 6MF.
R R R R R R B. Medical Outlets 40MF and 42MF The busbar 210XP supplies 115 VAC 400 Hz 1-phase to the socket 40MF, and is protected by the circuit breaker 18MF. The busbar 20PP supplies 28 V DC, 1-phase to the socket 42MF, and is protected by the circuit breaker 17MF.
CES
Electrical Power Sockets - Location
Figure 001
EFF : 301-399, 25-67-00 Page 2
May 01/04
CES
R R Electrical Power Sockets - Location Figure 001A
R EFF : 401-499, 25-67-00 Page 3 Aug 01/05
CES
Electrical Power Supply for Sockets - Schematic
Figure 002
CES
R Electrical Power Supply for Sockets - Schematic
R Figure 002A
EFF : 401-499, 25-67-00 Page 5
Aug 01/05
CES
RAPID DECOMPRESSION SAFETY SYSTEM - DESCRIPTION AND OPERATION 中国航空网 www.aero.cn 航空翻译 www.aviation.cn 本文链接地址:A320飞机维护手册 AMM EQUIPMENT/FURNISHINGS 设备4(171)