(Ref. Fig. 402A/TASK 25-26-41-991-003) R **ON A/C 001-049, 101-105,
Subtask 25-26-41-020-054-A
A. Removal of the curtain rail:
(Ref. Fig. 402/TASK 25-26-41-991-003-A)
(1)
Remove the screws (3).
(2)
Remove the curtain and curtain rail (1).
(3)
Remove the fittings (4) from the curtain rail (1).
(4)
Remove the brackets.
(a)
Remove the screws (5) and the brackets (2).
(b)
Remove the screw (7), the washer (6) and the strap (8).
EFF : ALL
25-26-41Page 417
Aft Utility-Area Divider Figure 402/TASK 25-26-41-991-003-A
R EFF : 001-049, 101-105, 25-26-41 Page 418 May 01/05
CES
Aft Utility-Area Divider Figure 402A/TASK 25-26-41-991-003
R EFF : 151-199, 201-210, 301-399, 25-26-41 Page 419 Feb 01/05
CES
R **ON A/C 151-199, 201-210, 301-399,
Subtask 25-26-41-020-054
A. Removal of the curtain rails:
(Ref. Fig. 402A/TASK 25-26-41-991-003)
NOTE : The procedure to remove all the curtain rails is the same.
____
(1)
Remove the curtain rail(s) (1).
(a)
Loosen the screws (2).
(b)
Hold the curtain rail(s) (1) in position, remove the screws (2) and the curtain rail(s) (1).
(2)
Remove the fittings (3) from the curtain rail(s) (1).
(3)
Remove the screws (5) and the brackets (4).
(4)
Remove the screw(s) (7), the washer(s) (8) and the strap(s) (6).
**ON A/C ALL
TASK 25-26-41-400-003
Installation of the Aft Curtain Rail
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
11-00-00-400-007 Installation of the ESSO (Scotchcal Labels) 24-42-00-861-001 Energize the Ground Service Network from the External Power 24-42-00-862-001 De-energize the Ground Service Network Supplied from
the External Power
25-26-41-000-013 Removal of the Curtains
25-26-41-400-013 Installation of the Curtains
AMM 11-32-25 P.Block 001 INTERIOR PLACARDS (SEE ALSO 11-42-25)
R **ON A/C 001-049, 101-105,
25-26-41-991-003-A Fig. 402
**ON A/C 151-199, 201-210, 301-399,
25-26-41-991-003 Fig. 402A
EFF : ALL
25-26-41Page 421
**ON A/C ALL
3. Job Set-up
__________
Subtask 25-26-41-860-051
A. Aircraft Maintenance Configuration
(1)
Make sure that the ground service network is energized (Ref. TASK 24-42-00-861-001).
(2)
Make sure that the AFT Curtains are removed (Ref. TASK 25-26-41-000-013).
4. Procedure
_________ R **ON A/C 001-049, 101-105,
(Ref. Fig. 402/TASK 25-26-41-991-003-A)
**ON A/C 151-199, 201-210, 301-399,
(Ref. Fig. 402A/TASK 25-26-41-991-003)
**ON A/C ALL
Subtask 25-26-41-210-066
A. Preparation for Installation
(1)
Clean the component interface and/or the adjacent area.
(2)
Do an inspection of the component interface and/or the adjacent area.
(3)
Make sure that the parts retained from the removed component are clean and in the correct condition.
EFF : ALL
25-26-41Page 422
R **ON A/C 001-049, 101-105,
Subtask 25-26-41-420-053-A
B. Installation of the curtain rail:
(Ref. Fig. 402/TASK 25-26-41-991-003-A)
(1)
Install the brackets.
(a)
Put the strap (8) and the washer (6) in position and install the screw (7).
(b)
Put the brackets (2) in position and install the screws (5).
(2)
Install the curtain rail.
(a) Put the fittings (4) in position in the curtain rail (1).
(b) Put the curtain rail (1) in position and install the screws (3). **ON A/C 151-199, 201-210, 301-399,
Subtask 25-26-41-420-053
B. Installation of the curtain rail(s):
(Ref. Fig. 402A/TASK 25-26-41-991-003)