**ON A/C ALL
TASK 25-26-41-400-001
Installation of the Forward Curtain Rail
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
11-00-00-400-007 Installation of the ESSO (Scotchcal Labels) 23-73-22-400-001 Installation of the Attendant Indication Panel 320RH 24-42-00-861-001 Energize the Ground Service Network from the External
Power 24-42-00-862-001 De-energize the Ground Service Network Supplied from
the External Power
25-26-41-000-013 Removal of the Curtains
25-26-41-400-013 Installation of the Curtains
AMM 11-32-25 P.Block 001 INTERIOR PLACARDS (SEE ALSO 11-42-25)
R **ON A/C 001-049, 101-105, 201-210,
25-26-41-991-001-B Fig. 401
**ON A/C 151-199,
25-26-41-991-001-A Fig. 401A
**ON A/C 301-399,
25-26-41-991-001-C Fig. 401B
EFF : ALL
25-26-41Page 410
**ON A/C ALL
3. Job Set-up
__________
Subtask 25-26-41-860-050
A. Aircraft Maintenance Configuration
(1)
Make sure that the ground service network is energized (Ref. TASK 24-42-00-861-001).
(2)
Make sure that the FWD Curtains are removed (Ref. TASK 25-26-41-000-013).
4. Procedure
_________ R **ON A/C 001-049, 101-105, 201-210,
(Ref. Fig. 401/TASK 25-26-41-991-001-B)
**ON A/C 151-199,
(Ref. Fig. 401A/TASK 25-26-41-991-001-A)
**ON A/C 301-399,
(Ref. Fig. 401B/TASK 25-26-41-991-001-C)
**ON A/C ALL
Subtask 25-26-41-210-065
A. Preparation for Installation
(1)
Clean the component interface and/or the adjacent area.
(2)
Do an inspection of the component interface and/or the adjacent area.
(3)
Make sure that the parts retained from the removed component are clean and in the correct condition.
EFF : ALL
25-26-41Page 411
R **ON A/C 001-049, 101-105, 201-210,
Subtask 25-26-41-420-075
B. Installation of the curtain rail:
(Ref. Fig. 401/TASK 25-26-41-991-001-B)
(1)
Install the brackets:
(a)
Put the straps (24) and the washers (23) in position and install the screws (22).
(b)
Put the brackets (8) in position and install the screws (9).
(c)
Put the brackets (13) in position and install the screws (14).
(d)
Put the fittings (15), (18) and (19) in position.
(2)
Install the curtain rail (2).
(a)
Install the washers (10), (25), (26) and (11) as identified to the brackets (8).
(b)
Install the curtain rail (2) to the brackets (8).
(c)
Install the washers (11) and the retaining rings (12).
(3)
Install the curtain rail (1).
(a)
Put the curtain rail (1) and the bracket (17) in position and install the screws (16).
(b)
Put the end cap (20) in position and install the screw (21).
(4)
Install the end panels.
(a)
Install the end panels (7) on the holders (4) of the overhead stowage compartment.
(b)
Install the washers (6) and the screws (5).
(c)
Close the doors (3) of the overhead stowage compartment.
(d)
Install the Attendant Indication Panel 320RH1 (Ref. TASK 23-73-22-400-001)
**ON A/C 151-199,
Subtask 25-26-41-420-075-A
B. Installation of the curtain rails:
(Ref. Fig. 401A/TASK 25-26-41-991-001-A)
(1)
Install the brackets.
(a)
Put the straps (28) and the washers (29) in position and install the screws (30).
(b)
Put the bracket (20) in position and install the screws (19).
(c)
Put the bracket (26) and the washers (24) in position and install the screws (23).