 (d)
 Put the brackets (8) in position and install the screws (18).

 

 (2)
 Install the curtain rail (2).

 (a)
 Put the fittings (12) and (27) in position.

 (b)
 Put the curtain rail (2) in position and install the screws (25).

 (c)
 Install the washer (21) and the retaining ring (22).

 

 (3)
 Install the curtain rail (1).

 (a)
 Put the fittings (11) and (17) in position.

 (b)
 Put the curtain rail (1) in position.

 (c)
 Put the bracket (15) in position, install the screws (13), (14) and (16).

 

 (4)
 Install the end panels (7).

 (a)
 Install the end panels (7) on the holders (4) of the overhead stowage compartment.

 (b)
 Install the washers (6) and the screws (5).

 (c)
 Put the end cap (10) in position, install the screw (9).

 (d)
 Close the door (3) of the overhead stowage compartment.

 

 


 (e) Install the attendant indication panel 320RH1 (Ref. TASK 23-73-
22-400-001). 
R  **ON A/C 301-399, 
R  Subtask 25-26-41-420-075-B 
R  B. Installation of the Curtain Rails: 
R  (Ref. Fig. 401B/TASK 25-26-41-991-001-C) 
R  (1) Installation of the Straps: 
R  (a) Put the straps (22) and the washers (23) in position and install 
R  the screws (24). 
R  (2) Installation of the Curtain Rail (1): 
R  (a) Put the brackets (14), (15), and (16) in position and install the 
R  screws (17). 
R  (b) Put the fittings (11) and (12) in the curtain rail (1) in 
R  position. 
R  (c) Put the curtain rail (1) in position and install the screws (10). 
R  (d) Put the end caps (9) in position and install the screws (8). 
R  (3) Installation of the Curtain Rail (2): 
R  (a) Put the fitting (13) in position and install the screws (10) but 
R  do not tighten. 
R  (b) Put the curtain rail (2) in position and install the washer (19), 
R  the retaining ring (20) and tighten the screw (10). 
R  (c) Install the end panel (5) on the holders (4) of the overhead 
R  stowage compartment. 
R  (d) Install the washer (7) and the screw (6). 
R  (e) Close the door (3) of the overhead stowage compartment. 
R  (f) Install the attendant indication panel 320RH1 (Ref. TASK 23-73-
R  22-400-001). 

 CES  **ON A/C ALL


 5. Close-up
________ Subtask 25-26-41-410-060
 A. Close Access
 (1)
 Install the FWD Curtains (Ref. TASK 25-26-41-400-013)

 (2)
 Make sure that the work area is clean and clear of tool(s) and other items.

 (3)
 Make sure that all of the placards of the retained/new components are in the correct position and in a good condition.

 (4)
 If necessary install new placards (Ref. TASK 11-00-00-400-007) and (Ref. AMM 11-32-25 P.Block 001).


 Subtask 25-26-41-862-051
 B. De-energize the ground service network
 (Ref. TASK 24-42-00-862-001).

 

 TASK 25-26-41-000-003
 Removal of the Aft Curtain Rail

 1.
 Reason for the Job

__________________
 Self Explanatory


 2.
 Job Set-up Information


______________________
 A. Referenced Information
 -------------------------------------------------------------------------------
REFERENCE  DESIGNATION
 -------------------------------------------------------------------------------
24-42-00-861-001  Energize the Ground Service Network from the External Power
 25-26-41-000-013  Removal of the Curtains
R **ON A/C 001-049, 101-105,
 25-26-41-991-003-A Fig. 402
 **ON A/C 151-199, 201-210, 301-399,

 25-26-41-991-003 Fig. 402A
 **ON A/C ALL

 3. Job Set-up
__________
 Subtask 25-26-41-861-050

 A. Energize the ground service network
 (Ref. TASK 24-42-00-861-001).

 Subtask 25-26-41-010-075
 B. Get Access
 (1) Remove the AFT Curtains (Ref. TASK 25-26-41-000-013)
 EFF : ALL
25-26-41Page 416


 4. Procedure
_________ R **ON A/C 001-049, 101-105,
 (Ref. Fig. 402/TASK 25-26-41-991-003-A)
 