_ valve 1698GM and put it back into its stowage.
 4 Install the blanking cap on the reservoir fill valve.
_
 (14)
 Install the blanking caps on the drain valves of the three hydraulic reservoirs.

 (15)
 Do the EIS stop procedure (Ref. TASK 31-60-00-860-002).

 (16)
 De-energize the aircraft electrical circuits (Ref. TASK 24-41-00-862-002).

 (17)
 Remove the warning notice(s).


 1EFF : ALL 1 29-31-00Page 514 1 1 Nov 01/02R 1 1 1CES 1


 Subtask 29-31-00-410-053
 B. Close Access
 (1)
 Make sure that the work area is clean and clear of tool(s) and other items.

 (2)
 Close the right main door of the main landing gear (Ref. TASK 32-12-00-410-001).

 (3)
 Remove the ground support and maintenance equipment, the special and standard tools and all other items.

 (4)
 Close the access doors 196BB, 195BB, 197CB, 197EB, 197FB, 198CB.

 


 INDICATOR - RESERVOIR HYDRAULIC QUANTITY (1834GQ) - REMOVAL/INSTALLATION
________________________________________________________________________ TASK 29-31-21-000-001 Removal of the Quantity Indicator (1834GQ)
 1.
 Reason for the Job

__________________
 Self Explanatory


 2.
 Job Set-up Information


______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific blanking caps
 No specific circuit breaker(s) safety clip(s)

 B. Referenced Information
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
29-31-21-991-001 Fig. 401
 3. Job Set-up
__________ Subtask 29-31-21-865-050
 A. Open, safety and tag this(these) circuit breaker(s):
 -------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------
121VU HYDRAULIC/HYD/QTY/IND 1831GQ P35
 Subtask 29-31-21-010-050
 B. Open the access door 197CB.


 4. Procedure
_________
 (Ref. Fig. 401/TASK 29-31-21-991-001) Subtask 29-31-21-020-050
 A. Removal of the Quantity Indicator
 (1)
 Loosen the screws (1).

 (2)
 Pull the quantity indicator (2) out of the ground service panel (3) of the Green hydraulic system.

 (3)
 Remove the electrical connector (4) from the quantity indicator (2).

 (4)
 Put blanking caps on the disconnected electrical connectors.

 


 Quantity Indicator
 Figure 401/TASK 29-31-21-991-001
 1EFF :  ALL  1  29-31-21 Page 403 
1  1  Feb 01/98
 1  1
 1CES  1

 

 TASK 29-31-21-400-001
 Installation of the Quantity Indicator (1834GQ)

 1.
 Reason for the Job

__________________
 Self Explanatory


 2.
 Job Set-up Information


______________________
 A. Referenced Information
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
32-12-00-010-001 Open the Main Gear Doors for Access 32-12-00-410-001 Close the Main Gear Doors after Access 29-31-21-991-001 Fig. 401
 3. Job Set-up
__________ Subtask 29-31-21-860-050
 A. Make sure that the access door 197CB is open. Subtask 29-31-21-865-051
 B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged
 -------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------
121VU HYDRAULIC/HYD/QTY/IND 1831GQ P35
 4. Procedure
_________ (Ref. Fig. 401/TASK 29-31-21-991-001) Subtask 29-31-21-420-050
 A. Installation of the Quantity Indicator
 NOTE : It is possible to install a quantity indicator with the unit

____ LITERS or US GAL shown on the dial. Make sure that you install the related quantity indicator for your hydraulic system.


 (1)
 Clean the component interface and/or the adjacent area.
 
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM HYDRAULIC POWER 液压6(128)