No specific safety barriers
 B. Referenced Information
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
12-11-28-650-001 General Refuel/Defuel Safety Procedures 12-34-24-869-001 Aircraft Grounding for the Refuel/Defuel Operations 24-41-00-861-002 Energize the Aircraft Electrical Circuits from the
 External Power 24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied
 from the External Power 28-00-00-910-001 Fuel Safety Procedures 28-25-00-650-001 Pressure Defuel 31-60-00-860-001 EIS Start Procedure 31-60-00-860-002 EIS Stop Procedure
 1EFF : ALL 1 28-25-00Page 523 1 1 May 01/05R 1 1 1CES 1


 -------------------------------------------------------------------------------
REFERENCE DESIGNATION -------------------------------------------------------------------------------
R  **ON A/C 001-049, 052-099, 101-149, 151-199, 201-299, 301-399, 401-499,
 28-25-00-991-011 **ON A/C 051-051, Fig. 501
 28-25-00-991-011-A **ON A/C ALL Fig. 501A
R  28-25-00-991-013 Fig. 502 **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 401-499,
 28-25-00-991-014 **ON A/C 301-399, Fig. 503
 28-25-00-991-014-A **ON A/C ALL Fig. 503A
R  3. Job Set-up__________ **ON A/C 001-049, 052-099, 101-149, 151-199, 201-299, 301-399, 401-499,
 (Ref. Fig. 501/TASK 28-25-00-991-011) **ON A/C 051-051,
 (Ref. Fig. 501A/TASK 28-25-00-991-011-A)

 1EFF : ALL 1 28-25-00Page 524 1 1 Aug 01/05 1 1 1CES 1 **ON A/C ALL


 (Ref. Fig. 502/TASK 28-25-00-991-013)
 Subtask 28-25-00-941-074

 A. Safety Precautions
 WARNING : OBEY THE FUEL SAFETY PROCEDURES.

_______
 (1)
 You must obey the fuel safety procedures (Ref. TASK 28-00-00-910-001) when you do work on the fuel system.

 (2)
 You must obey the refuel/defuel safety procedures (Ref. TASK 12-11-28-650-001) when you do work on the refuel/defuel system.


 (3) Put the safety barriers in position.
 Subtask 28-25-00-010-059

 B. Get Access
 (1) Open the access door 192MB. NOTE : Do not keep the door open longer than necessary because the
____
 battery can discharge.


R **ON A/C 001-049, 052-099, 101-149, 151-199, 201-299, 301-399, 401-499,
 Subtask 28-25-00-860-057
 C. Aircraft Maintenance Configuration
 (1) Make sure that the aircraft and the fuel tanker/pump unit are grounded correctly (Ref. TASK 12-34-24-869-001).
 NOTE : Bonding is essential, grounding is recommended.
____
 (2)
 Make sure that the chocks do not touch the tires. The weight of the fuel can lower the aircraft and cause the chocks to catch.

 (3)
 Remove the refuel coupling cap 41QM.

 (4)
 Make sure that the hose-coupling of the fuel tanker/pump unit is clean.


 1EFF : ALL 1 28-25-00Page 525 1 1 Aug 01/05 1 1 1CES 1 1EFF : ALL 1 28-25-00Page 526 1 1 May 01/05 1 1 1CES 1


 (5) Connect the hose-coupling of the fuel tanker/pump unit to the
 aircraft refuel/defuel coupling.
 (6) Set the fuel tanker/pump unit to the refuel mode.
 (7) Energize the aircraft electrical circuits (Ref. TASK 24-41-00-861-
002).
 (8) Energize the Electronic Centralized Aircraft Monitoring (ECAM) system
 (Ref. TASK 31-60-00-860-001).
 (9) On the ECAM CP, push (in) the FUEL system page pushbutton switch. 
R  **ON A/C 051-051, 
R  Subtask 28-25-00-860-057-A 
R  C. Aircraft Maintenance Configuration 
R  (1) Make sure that the aircraft and the fuel tanker/pump unit are 
R  grounded correctly (Ref. TASK 12-34-24-869-001). 
R  NOTE : Bonding is essential, grounding is recommended.____ 
R  (2) Make sure that the chocks do not touch the tires. The weight of the 
R  fuel can lower the aircraft and cause the chocks to catch. 
R  (3) Remove the applicable refuel coupling cap 101QM (41QM). 
R  (4) Make sure that the hose-coupling of the fuel tanker/pump unit is 
R  clean. 
R  (5) Connect the hose-coupling of the fuel tanker/pump unit to the 
R  aircraft refuel/defuel coupling. 
R  (6) Set the fuel tanker/pump unit to the refuel mode. 
R  (7) Energize the aircraft electrical circuits (Ref. TASK 24-41-00-861-
R  002). 
R  (8) Energize the Electronic Centralized Aircraft Monitoring (ECAM) system 
 