FOR 12QM
-
install 522AT
FOR 13QM
-
install 622AT.
1EFF : ALL 1 28-24-00Page 518 1 1 May 01/04R 1 1 1CES 1
Subtask 28-24-00-860-061
B. Aircraft Maintenance Configuration
(1)
On the ECAM CP, put the BRT switches to the OFF position.
(2)
De-energize the aircraft electrical networks (Ref. TASK 24-41-00-862-002).
Subtask 28-24-00-942-050
C. Removal of Equipment
(1)
Remove the safety barriers.
(2)
Remove the warning notice(s).
(3)
Remove the access platform(s).
(4)
Remove the ground support and maintenance equipment, the special and standard tools and all other items.
1EFF : ALL 1 28-24-00Page 519 1 1 May 01/04R 1 1 1CES 1
TASK 28-24-00-720-001- 01
Functional Test of the LP Fuel Shut Off Valves
WARNING : PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU
_______ START A TASK ON OR NEAR:
-
THE FLIGHT CONTROLS
-
THE FLIGHT CONTROL SURFACES
-
THE LANDING GEAR AND THE RELATED DOORS
-COMPONENTS THAT MOVE.
WARNING : MAKE SURE THAT THE GROUND SAFETY-LOCKS ARE IN POSITION ON THE LANDING
_______ GEAR.
1. Reason for the Job__________________
Refer to the MMEL TASK: 28-40-06-B)
Indications on ECAM FUEL page
Engine LP valve indication
2. Job Set-up Information______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------
REFERENCE QTY DESIGNATION
-------------------------------------------------------------------------------
No specific safety barriers No specific warning notice No specific access platform 3 m (9 ft. 10 in.)
1EFF : ALL 1 28-24-00Page 520 1 1 May 01/04R 1 1 1CES 1
B. Referenced Information
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
24-41-00-861-002 Energize the Aircraft Electrical Circuits from the External Power 24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied
from the External Power
28-00-00-910-001 Fuel Safety Procedures
31-60-00-860-001 EIS Start Procedure
R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 401-499,
28-24-00-991-002 Fig. 501
**ON A/C 301-399,
28-24-00-991-002-A Fig. 501A
**ON A/C ALL
28-24-00-991-001 Fig. 502
__________
3. Job Set-up
R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 401-499,
(Ref. Fig. 501/TASK 28-24-00-991-002)
**ON A/C 301-399,
(Ref. Fig. 501A/TASK 28-24-00-991-002-A)
**ON A/C ALL
(Ref. Fig. 502/TASK 28-24-00-991-001)
1EFF : ALL 1 28-24-00Page 521 1 1 Aug 01/05 1 1 1CES 1 Subtask 28-24-00-941-059
A. Safety Precautions
WARNING : OBEY THE FUEL SAFETY PROCEDURES.
_______
(1)
You must obey the fuel safety procedures (Ref. TASK 28-00-00-910-001) when you do work on the fuel system.
(2)
Put the safety barriers in position.
(3)
Put a warning notice in the cockpit to tell persons not to operate the APU or bleed air.
Subtask 28-24-00-010-055
B. Get Access
(1)
Put the access platform in position.
(2)
Remove the applicable access panel(s):
FOR 12QM
-remove 522AT
FOR 13QM
-remove 622AT. Subtask 28-24-00-860-062
C. Aircraft Maintenance Configuration
(1)
Make sure that the APU does not operate and there is no bleed air.
(2)
Energize the aircraft electrical circuits (Ref. TASK 24-41-00-861-002).
(3)
Do the EIS start procedure (ECAM only) (Ref. TASK 31-60-00-860-001).
1EFF : ALL 1 28-24-00Page 522 1 1 May 01/04R 1 1 1CES 1
Subtask 28-24-00-865-069
D. Make sure that this(these) circuit breaker(s) is(are) closed:
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------49VU FUEL/LP VALVE/MOT1/ENG2 2QG A09 49VU FUEL/LP VALVE/MOT1/ENG1 1QG A08 121VU FUEL/LP VALVE/MOT2/ENG2 4QG M26 121VU FUEL/LP VALVE/MOT2/ENG1 3QG M25