_______
AVAILABLE.
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific access platform 1.50 m (4 ft. 11 in.)
B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
R 54-51-21-000-001 Removal of the Pylon Lateral Access-Doors 71-00-00-000-042 Removal of the Power Plant 71-13-11-000-040 Removal of the Fan Cowl Doors 78-32-11-000-040 Removal of the Left or Right Half Door of Thrust
Reverser
54-51-29-991-001 Fig. 401
3. Job Set-up
__________
Subtask 54-51-29-941-050
A. Safety Precautions
(1) On the center pedestal, on the ENG panel 115VU:
(a) Put a warning notice to tell persons not to start the engine.
1EFF : ALL 1 54-51-29Page 401 1 1 Nov 01/04 1 1 1CES 1
(2)
Make sure that the engine 1(2) shutdown occurred not less than 5 minutes before you do this procedure.
(3)
On the overhead maintenance panel 50VU:
(a)
Make sure that the ON legend of the ENG/FADEC GND PWR/1(2) pushbutton switch is off.
(b)
Put the warning notice to tell persons not to energize the FADEC 1(2).
Subtask 54-51-29-020-051
B. Removal of the Components
(1)
Remove the fan cowl doors (Ref. TASK 71-13-11-000-040).
(2)
Remove the thrust reverser cowl doors (Ref. TASK 78-32-11-000-040).
(3) Remove the power plant (Ref. TASK 71-00-00-000-042).
Subtask 54-51-29-010-050
C. Get Access
(1) Put an access platform in position:
(a) At zone 410 for the left pylon.
(b) At zone 420 for the right pylon. R (2) Remove the pylon lateral access-doors (Ref. TASK 54-51-21-000-001):
-
For the left pylon: 415BL, 415BR.
-
For the right pylon: 425BL, 425BR.
(3) Remove the panels:
-
For the left pylon: 473AL, 473AR.
-
For the right pylon: 483AL, 483AR.
4. Procedure
_________
Subtask 54-51-29-020-050
A. Removal of the Hoisting Fittings
(Ref. Fig. 401/TASK 54-51-29-991-001)
(1)
Remove the nuts (1) and discard them. Remove the washers (2).
(2)
Remove the hoisting fittings (3).
Hoisting Fitting
Figure 401/TASK 54-51-29-991-001
1EFF : ALL 1 54-51-29 Page 404
1 1 Feb 01/98
1 1
1CES 1
TASK 54-51-29-400-001
Installation of the Hoisting Fitting
1. Reason for the Job
__________________
Self Explanatory
2. Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------
REFERENCE QTY DESIGNATION
-------------------------------------------------------------------------------
No specific 19 mm (0.7480 in.) dia. bar
No specific Torque Wrench : range 2.00 to 20.00 m.daN
(15.00 to 150.00 lbf.ft)
B. Expendable Parts
-------------------------------------------------------------------------------
FIG.ITEM |DESIGNATION |IPC-CSN
-------------------------------------------------------------------------------
1 nuts 54-51-29 02A-030
C. Referenced Information
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
R 54-51-21-400-001 Installation of the Pylon Lateral Access-Doors 71-00-00-400-042 Installation of the Power Plant 71-13-11-400-040 Installation of the Fan Cowl Doors 78-30-00-481-041 Make the Thrust Reverser Unserviceable for Maintenance 78-32-11-400-040 Installation of the Left or Right Half Door of Thrust Reverser 54-51-29-991-001 Fig. 401
3. Job Set-up
__________
Subtask 54-51-29-860-050
A. Aircraft Maintenance Configuration