_______
 AVAILABLE.
 1.
 Reason for the Job
__________________
 Self Explanatory
 2.
 Job Set-up Information
______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific  access platform 1.50 m (4 ft. 11 in.)
 B. Referenced Information
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
R  54-51-21-000-001 Removal of the Pylon Lateral Access-Doors 71-00-00-000-042 Removal of the Power Plant 71-13-11-000-040 Removal of the Fan Cowl Doors 78-32-11-000-040 Removal of the Left or Right Half Door of Thrust
 Reverser
 54-51-29-991-001 Fig. 401
 3. Job Set-up
__________
 Subtask 54-51-29-941-050
 A. Safety Precautions
 (1) On the center pedestal, on the ENG panel 115VU:
 (a) Put a warning notice to tell persons not to start the engine.
 1EFF : ALL 1 54-51-29Page 401 1 1 Nov 01/04 1 1 1CES 1
 (2)
 Make sure that the engine 1(2) shutdown occurred not less than 5 minutes before you do this procedure.
 (3)
 On the overhead maintenance panel 50VU:
 (a)
 Make sure that the ON legend of the ENG/FADEC GND PWR/1(2) pushbutton switch is off.
 (b)
 Put the warning notice to tell persons not to energize the FADEC 1(2).
 Subtask 54-51-29-020-051
 B. Removal of the Components
 (1)
 Remove the fan cowl doors (Ref. TASK 71-13-11-000-040).
 (2)
 Remove the thrust reverser cowl doors (Ref. TASK 78-32-11-000-040).
 (3) Remove the power plant (Ref. TASK 71-00-00-000-042).
 Subtask 54-51-29-010-050
 C. Get Access
 (1) Put an access platform in position:
 (a) At zone 410 for the left pylon.
 (b) At zone 420 for the right pylon. R (2) Remove the pylon lateral access-doors (Ref. TASK 54-51-21-000-001):
 -
For the left pylon: 415BL, 415BR.
 -
For the right pylon: 425BL, 425BR.
 (3) Remove the panels:
 -
For the left pylon: 473AL, 473AR.
 -
For the right pylon: 483AL, 483AR.
 4. Procedure
_________
 Subtask 54-51-29-020-050
 A. Removal of the Hoisting Fittings
 (Ref. Fig. 401/TASK 54-51-29-991-001)
 (1)
 Remove the nuts (1) and discard them. Remove the washers (2).
 (2)
 Remove the hoisting fittings (3).
 Hoisting Fitting 
 Figure 401/TASK 54-51-29-991-001 
 1EFF :  ALL  1  54-51-29 Page 404  
1  1  Feb 01/98 
 1  1 
 1CES  1
 TASK 54-51-29-400-001
 Installation of the Hoisting Fitting
 1. Reason for the Job
__________________
 Self Explanatory
 2. Job Set-up Information
______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------
REFERENCE QTY DESIGNATION
 -------------------------------------------------------------------------------
No specific 19 mm (0.7480 in.) dia. bar
 No specific Torque Wrench : range 2.00 to 20.00 m.daN
 (15.00 to 150.00 lbf.ft)
 B. Expendable Parts
 -------------------------------------------------------------------------------
FIG.ITEM |DESIGNATION |IPC-CSN
 -------------------------------------------------------------------------------
1 nuts 54-51-29 02A-030
 C. Referenced Information
 -------------------------------------------------------------------------------
REFERENCE DESIGNATION
 -------------------------------------------------------------------------------
R 54-51-21-400-001 Installation of the Pylon Lateral Access-Doors 71-00-00-400-042 Installation of the Power Plant 71-13-11-400-040 Installation of the Fan Cowl Doors 78-30-00-481-041 Make the Thrust Reverser Unserviceable for Maintenance 78-32-11-400-040 Installation of the Left or Right Half Door of Thrust Reverser 54-51-29-991-001 Fig. 401
 3. Job Set-up
__________
 Subtask 54-51-29-860-050
 A. Aircraft Maintenance Configuration
 