 Subtask 24-41-00-861-053
 A. Energize the aircraft electrical circuit from the engine 1(2)
 (1)
 Start the engine 1(2) with the automatic procedure (Ref. TASK 71-00-00-710-003): - on the ELEC panel 35VU, the FAULT legend of the GEN 1(2) pushbutton

 switch goes off.

 (2)
 Do the EIS start procedure (Upper ECAM DU and lower ECAM DU only) (Ref. TASK 31-60-00-860-001).

 (3)
 On the ECAM control panel, push the ELEC key (on the lower ECAM DU, the ELEC page comes into view).

 (4)
 On the ELEC page, make sure that:

 -
the GEN 1(2) indication comes into view white,

 -
the parameters related to GEN 1(2) come into view green,

 -
the line between GEN 1(2) and AC 1(2) comes into view green,

 -
the GEN 2(1) indication and the related parameters come into view green,

 -
the APU GEN indication and the related parameters come into view green,

 -
the line between APU GEN and AC2(1) comes into view green,

 -
the line between APU GEN and AC1(2) goes out of view.

 

 (5)
 On the ELEC panel 35VU, release the APU GEN pushbutton switch:

 -the OFF legend of the APU GEN pushbutton switch comes on.

 (6)
 On the ELEC page, make sure that:

 -
the APU GEN indication comes into view amber and the OFF indication white,

 -
the line between GEN1(2) and AC2(1) comes into view green,

 -
the line between APU GEN and AC2(1) goes out of view.

 

 (7)
 Stop the APU (Ref. TASK 24-41-00-862-002).


R 1EFF : ALL 1 24-41-00Page 210 1 1 May 01/05 1 1 1CES 1


 TASK 24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied from the External Power
 1.
 Reason for the Job

__________________
 Self Explanatory


 2.
 Job Set-up Information


______________________
 A. Referenced Information
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-41-00-991-001 Fig. 201
 3. Job Set-up
__________
 Subtask 24-41-00-869-067

 A. Not Applicable
 4. Procedure
_________ R **ON A/C 001-049, 051-060, 101-102, 201-201,
 Subtask 24-41-00-862-051
 A. De-energize the aircraft electrical circuits from the external power
 (1)
 On the ELEC panel 35VU, push and release the BAT1 and BAT2 pushbutton switches:

 -the OFF legends come on.

 (2)
 On the panel 35VU, push the EXT PWR pushbutton switch:

 -
the ON legend goes off,

 -
the AVAIL legend comes on.

 

 (3)
 The aircraft electrical circuits are correctly de-energized if:

 (a)
 On the panel 35VU, these legends go off:

 -
the FAULT legend of the GEN1 and GEN2 pushbutton switches,

 -
the OFF legend of the BAT1 and BAT2 pushbutton switches,

 -
the OFF legend of the GALLEY pushbutton switch.

 

 (b)
 On the panel 108VU, the EXT PWR/NOT IN USE indicator light comes on.

 

 

 

R **ON A/C 061-099, 103-149, 151-199, 202-299, 301-399, 401-499,
 Subtask 24-41-00-862-051-A
 A. De-energize the aircraft electrical circuits from the external power
 (1)
 On the ELEC panel 35VU, push and release the BAT1 and BAT2 pushbutton switches:

 -the OFF legends come on.

 (2)
 On the panel 35VU, push the EXT PWR pushbutton switch:

 -
the ON legend goes off,

 -
the AVAIL legend comes on.

 

 (3)
 The aircraft electrical circuits are correctly de-energized if:

 (a)
 On the panel 35VU, these legends go off:

 -
the FAULT legend of the GEN1 and GEN2 pushbutton switches,

 -
the OFF legend of the BAT1 and BAT2 pushbutton switches,

 -
the OFF legend of the GALY and CAB pushbutton switch.

 

 (b)
 On the panel 108VU, the EXT PWR/NOT IN USE indicator light comes on.

 


 **ON A/C ALL
 5. Close-up
________
 (Ref. Fig. 201/TASK 24-41-00-991-001)
 Subtask 24-41-00-080-051
 A. Obey the instructions given with the ground power unit and stop the ground power unit.
 -
On the panel 35VU, all the pushbutton switch legends are off.
 