(1)
Do these tests:
-
(Ref. TASK 24-26-00-710-002),
-
(Ref. TASK 29-12-00-710-001),
-
(Ref. TASK 21-26-00-710-002),
-
(Ref. TASK 30-42-00-710-001),
-
(Ref. TASK 28-21-00-710-001),
-
(Ref. TASK 33-51-00-710-001),
-
(Ref. TASK 29-31-00-710-001),
-
(Ref. TASK 33-25-00-710-001),
-
(Ref. TASK 24-24-00-710-001),
-
(Ref. TASK 30-31-00-710-001),
-
(Ref. TASK 24-32-00-710-001).
(2)
Energize the aircraft electrical circuits from the external power (Ref. TASK 24-41-00-861-002).
Subtask 24-22-17-860-058-A
G. Aircraft Maintenance Configuration
FOR 42XU4
(1)
Do these tests:
-
(Ref. TASK 24-26-00-710-002),
-
(Ref. TASK 21-26-00-710-002),
-
(Ref. TASK 30-42-00-710-001),
-
(Ref. TASK 33-25-00-710-001),
-
(Ref. TASK 28-21-00-710-001),
-
(Ref. TASK 30-31-00-710-001),
-
(Ref. TASK 34-11-00-710-001),
-
(Ref. TASK 33-21-00-710-001),
-
(Ref. TASK 24-24-00-710-001),
-
(Ref. TASK 24-32-00-710-001).
(2)
Energize the aircraft electrical circuits from the external power (Ref. TASK 24-41-00-861-002).
**ON A/C 001-049, 051-099, 101-105, 151-199, 201-228, 301-302,
Subtask 24-22-17-865-050
H. Make sure that this(these) circuit breaker(s) is(are) closed:
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------
122VU ELEC/GALLEY/CNTOR 7MC S28
**ON A/C 001-049, 051-060, 101-102, 201-201,
122VU ELEC/GALLEY/CTL 1XA S26
**ON A/C 061-099, 103-105, 151-199, 202-228, 301-302,
122VU ELEC/GALY & CAB/CTL 1XA S26
**ON A/C 001-049, 051-099, 101-105, 151-199, 201-228, 301-302,
123VU FWD GALLEY/FEEDER F 16MC AC10 123VU AFT GALLEY/FEEDER E 14MC AF09
-------------------------------------------------------------------------------
PANEL ------ DESIGNATION ------------------------------------------------ IDENT. LOCATION-------------------------
**ON A/C 301-302,
123VU FWD GALLEY/FEEDER C 1MC AE03
123VU FWD GALLEY/FEEDER D 2MC AE02
123VU AFT GALLEY/FEEDER A 3MC AF04
**ON A/C 001-049, 051-060, 101-102, 201-201,
Subtask 24-22-17-710-050
J. Operational test
(1) Do this test:
-------------------------------------------------------------------------------ACTION RESULT -------------------------------------------------------------------------------
1. On the ECAM control panel:
-push the ELEC key to get the ELEC page.
2. On the ELEC panel 35VU:
-push the GALLEY pushbutton switch.
3. In the FWD and/or AFT galleys:
-energize all the items of
equipment.
4. On the MCDU:
-do the operational test of the Ground Power Control Unit (GPCU) (Ref. TASK 24-41-00-740-002).
On the lower ECAM display unit:
-
the ELEC page comes into view.
On the panel 35VU:
-
the OFF legend of the GALLEY
pushbutton switch goes off. On the lower ECAM display unit:
-
the white GALLEY SHED indication comes into view.
On the lower ECAM display unit:
-make sure that the electricalparameters (load, voltage and frequency) of the GEN1(2) are correct.
On the MCDU, on the AC GEN page:
-the TEST OK message comes into view(after some seconds).
**ON A/C 061-099, 103-105, 151-199, 202-228, 301-302,
Subtask 24-22-17-710-050-A
J. Operational test
(1) Do this test:
-------------------------------------------------------------------------------ACTION RESULT -------------------------------------------------------------------------------
1. On the ECAM control panel:
-push the ELEC key to get the ELEC page.
2. On the ELEC panel 35VU:
-push the GALY & CAB pushbutton switch.
3. In the FWD and/or AFT galleys:
-energize all the items of
equipment.
4. On the MCDU:
-do the operational test of the Ground Power Control Unit (GPCU) (Ref. TASK 24-41-00-740-002).
On the lower ECAM display unit:
-
the ELEC page comes into view.
On the panel 35VU:
-
the OFF legend of the GALY & CAB
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM ELECTRICAL POWER 电源1(121)