AC MAIN GENERATION - ADJUSTMENT/TEST
____________________________________
TASK 24-22-00-710-001
Operational Test of the Generator Line Contactor (GLC-1) Opening in the Smoke Procedure
1. Reason for the Job
__________________
Refer to the MPD TASK: 245100-01 Test to make sure that the generator line contactor 1 opens and test of the power supply of the two fuel pumps in smoke procedure.
2. Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-41-00-861-002 Energize the Aircraft Electrical Circuits from the External Power 24-41-00-861-002 Energize the Aircraft Electrical Circuits from the APU 24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied from the External Power 24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied
from the APU 31-60-00-860-001 EIS Start Procedure 31-60-00-860-002 EIS Stop Procedure 71-00-00-710-003 Engine Automatic Start 71-00-00-710-028 Engine Shutdown
3. Job Set-up
__________
Subtask 24-22-00-860-050
A. Aircraft Maintenance Configuration
(1)
Energize the aircraft electrical circuits
(Ref. TASK 24-41-00-861-002).
(2)
Do the EIS start procedure (Upper ECAM DU and lower ECAM DU only) (Ref. TASK 31-60-00-860-001).
(3)
Start the engine (Ref. TASK 71-00-00-710-003). NOTE : You can do this test: start engine No. 1 only. Energize the
____ electrical circuit No. 2 with an electrical ground power unit (Ref. TASK 24-41-00-861-002) or with the APU (Ref. TASK 24-41-00-861-002).
(4)
On the HYD/FUEL panel 40VU, make sure that the L TK PUMPS/1 AND 2 and R TK PUMPS/1 AND 2 pushbutton switches are pushed.
(5)
On the ECAM control panel, push the FUEL key. On the lower ECAM display unit, make sure that the L wing tank pumps 1 and 2 and R wing tank pumps 1 and 2 operate correctly.
Subtask 24-22-00-865-050
B. Make sure that this(these) circuit breaker(s) is(are) closed: -------------------------------------------------------------------------------
PANEL ------ DESIGNATION ------------------------------------ ------------------ IDENT. LOCATION-------------------
49VU FUEL/SMOKE/CONFIG/PUMP CTL 55QA A14
121VU FUEL/L WING TK/PUMP1 SPLY 1QA N23
121VU FUEL/R WING TK/PUMP1 SPLY 2QA Q23
121VU FUEL/PUMPS/1/R CTL AND L IND 4QA R28
121VU FUEL/PUMPS/1/L CTL AND R IND 3QA R23
123VU L WING TK/PUMP 1/STBY SPLY 11QA AD12
123VU R WING TK/PUMP 1/STBY SPLY 12QA AE12
4. Procedure_________
Subtask 24-22-00-710-050
A. Operational test of the GLC-1
------------------------------------------ACTION ------------------RESULT -------------------
-------------------------------------------------------------------------------
1. On the panel 121VU: On the panel 40VU:
- open the circuit breaker 1QA. - the FAULT legend of the L TK PUMPS/1 pushbutton switch comes on,
On the lower ECAM display unit:
- on the FUEL page, the pump No. 1 of the left tank no longer operates.
-------------------------------------------------------------------------------
ACTION RESULT -------------------------------------------------------------------------------