2. On the EMER ELEC PWR panel 21VU:
-release the GEN 1 LINE
pushbutton switch.

3. On the ECAM control panel:
-push the ELEC key.
4. On the ECAM control panel:
-push the FUEL key.
5. On the panel 121VU:
-close the circuit breaker 1QA, - open the circuit breaker 2QA.
 6. On the EMER ELEC PWR panel 21VU:
-push the GEN 1 LINE pushbutton switch.
7. On the ECAM control panel:
-push the ELEC key.
8. On the panel 121VU:
-close the circuit breaker 2QA.
On the panel 21VU:
-
the OFF legend of the GEN 1 LINEpushbutton switch comes on.

 On the panel 40VU:

 -
the FAULT legend of the L TK PUMPS/1 pushbutton switch goes off.

On the lower ECAM display unit:

-
the generator No. 1 no longer supplies the AC 1 busbar. This busbar is supplied from the other generator with the transfer circuit.


On the lower ECAM display unit:
-
pump No. 1 of the left tank operates,

 -
pump No. 1 of the right tank operates.


There is no change.
On the panel 21VU:
-
the OFF legend of the GEN 1 LINEpushbutton switch goes off.

 On the panel 40VU:

 -
the FAULT legend of the R TK PUMPS/1 pushbutton switch comes on.


 On the lower ECAM display unit:
 - on the FUEL page, the pump No. 1 of the right tank no longer operates.
On the lower ECAM display unit:
-
the generator No. 1 supplies the circuit No. 1. The other generator supplies the circuit No. 2.

On the panel 40VU:

-
the FAULT legend of the R TK PUMPS/1 pushbutton switch goes off.

 


 -------------------------------------------------------------------------------ACTION RESULT -------------------------------------------------------------------------------
9. On the ECAM control panel: On the lower ECAM display unit:
 -push the FUEL key.  - the pump No. 1 of the right tank
 operates.

 5. Close-up
________
 Subtask 24-22-00-860-051
 A. Put the aircraft back to its initial configuration.
 (1)
 Stop the engines (Ref. TASK 71-00-00-710-028).

 (2)
 Do the EIS stop procedure
 (Ref. TASK 31-60-00-860-002).


 (3)
 De-energize the aircraft electrical circuits (Ref. TASK 24-41-00-862-002) or de-energize the APU (Ref. TASK 24-41-00-862-002).

 


 TASK 24-22-00-710-002 Operational Test of the Transfer Inhibition
 1. Reason for the Job
__________________
 Refer to the MPD TASK: 242200-01 Make sure that the transfer function is off when you release the BUS TIE pushbutton switch.
 2. Job Set-up Information
______________________
 A. Referenced Information
 -------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-41-00-861-002  Energize the Aircraft Electrical Circuits from the External Power 24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied from the External Power
 3. Job Set-up
__________ Subtask 24-22-00-860-052
 A. Aircraft Maintenance Configuration
 (1)
 Energize the aircraft electrical circuits
 (Ref. TASK 24-41-00-861-002).


 (2)
 On the ELEC panel 35VU, make sure that the BAT1 and BAT2 pushbutton switches are pushed.

 

 4. Procedure
_________

 Subtask 24-22-00-710-051
 A. Operational test of the transfer inhibition
 -------------------------------------------------------------------------------ACTION RESULT -------------------------------------------------------------------------------
1. On the panel 35VU:
-release the BUS TIE pushbutton switch.
2. On the panel 35VU:
-push the BUS TIE pushbutton switch.
5. Close-up
________
 Subtask 24-22-00-862-051In the cockpit, on the panel 35VU:
-loss of the power supply from theelectrical ground power unit: .the OFF legend of the BUS TIE pushbutton switch comes on.
 NOTE : This shows that the transfer
____ contactors are open. The batteries are the only available power supply.
In the cockpit, on the panel 35VU:
-the OFF legend of the BUS TIE
pushbutton switch goes off. All the aircraft electrical circuits are supplied.
 A. Put the aircraft back to its initial configuration.
 (1) De-energize the aircraft electrical circuits (Ref. TASK 24-41-00-862-002)


 CURRENT TRANSFORMER - AC (41XU1,41XU2,42XU1,42XU2,42XU3,42XU4,51XU1,51XU2)
 