____ containment shield was removed previously. Otherwise continue with step B.
(a)
Remove the blanking caps and connect the electrical connectors (7).
(b)
Make sure that the electrical connectors are clean and in the correct condition.
(c)
Install the washers (3) and (6), the nuts (4) and (5).
(d) Tighten the nuts (4) and (5). R **ON A/C 001-003, 051-099,
Subtask 49-23-15-410-051
B. Installation of the bottom Load-Compressor Containment-Shield (if previously removed)
(1)
Move the notched end of bottom load-compressor containment-shield
(14) carefully past the witness drain tube and under the LCIT wiring.
(2)
Adjust the load-compressor containment shield to align the shield spacer with the bleed-duct assy bolt (10) hole.
(3)
Loosely attach the load-compressor containment shield (14) with the bolts (10) and (15).
(4)
Make sure that the L-bracket (16) overlaps the outer diameter of the load-compressor containment-shield (14). Tighten the bolt (17).
(5)
Attach the bolts (11) and (18).
(6)
Install the clamp (12) of the LCIT wiring with bolt (13).
(7)
Torque all bolts to 80 lbf.in (0.90 m.daN).
(8)
Remove the blanking caps and connect the electrical connectors (7).
(9)
Make sure that the electrical connectors are clean and in the correct
condition.
(10) Install the washers (3) and (6), the nuts (4) and (5).
(11) Tighten the nuts (4) and (5). R **ON A/C 001-003, 051-099, 401-499,
Subtask 49-23-15-865-052
C. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s): 1KD, 2KD.
Subtask 49-23-15-710-050
D. Do the Self Test of the ECB (Ref. TASK 49-00-00-710-001).
5. Close-up
________
Subtask 49-23-15-410-050
A. Close Access
(1)
Make sure that the work area is clean and clear of tool(s) and other items.
(2)
Set the LIGHT control switch 11LJ to the OFF position.
(3)
Close the APU access doors 315AL, 316AR (Ref. TASK 52-41-00-410-001).
(4)
Remove the access platform(s).
Subtask 49-23-15-865-056
B.
Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------121VU APU/APU/CTL 2KD L42 121VU APU/ECB/SPLY 1KD L41
Subtask 49-23-15-860-052
C. Aircraft Maintenance Configuration
(1)
De-energize the aircraft electrical circuits (Ref. TASK 24-41-00-862-002).
(2)
Pressurize the reservoirs of the hydraulic systems. (Ref. TASK 29-14-00-614-002).
(3)
Remove the warning notice(s).
SENSOR - LOAD COMPRESSOR DISCHARGE TEMPERATURE - REMOVAL/INSTALLATION
_____________________________________________________________________
R **ON A/C 001-003, 051-099, 401-499,
TASK 49-23-16-000-001