NOTE : The installation of only one quick-coupler clamp is given. The
____ installation is applicable to all the clamps of this type.
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Expendable Parts
-------------------------------------------------------------------------------FIG.ITEM |DESIGNATION |IPC-CSN -------------------------------------------------------------------------------
28 O-rings 38-31-04 26F-100 28 O-rings 38-31-04 27D-070 28 O-rings 38-31-04 27F-070
1EFF : ALL 1 38-31-61Page 409 1 1 May 01/05R 1 1 1CES 1
B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 24-42-00-862-001 De-energize the Ground Service Network Supplied from
the External Power 38-31-00-680-001 Draining of the Toilet System 38-31-00-710-009 Operational Test of the Toilet Unit 38-31-00-790-002 Leak Test of the Vacuum Toilet System 38-31-62-400-001 Installation of the Liquid Level Transmitter (40MG) 38-31-63-400-001 Installation of the Liquid Level Sensor (41MG) 38-31-67-400-001 Installation of the Water Separator (3302MM) 38-31-74-400-001 Installation of the Waste Tank Drain Line 52-30-00-860-002 Close the FWD or AFT Cargo-Compartment Door with the
Yellow Electric Pump 53-43-11-400-001 Installation of the Support Struts 38-31-61-991-001 Fig. 401
3. Job Set-up
__________
Subtask 38-31-61-860-052
A. Aircraft Maintenance Configuration
(1)
Make sure that the ground service network is energized from the external power (Ref. TASK 24-42-00-861-001).
(2)
Make sure that the waste holding tank is drained (Ref. TASK 38-31-00-680-001).
Subtask 38-31-61-860-051
B. Installation of the Removed Components
(1) If removed install the level sensor 41MG to the waste holding tank 3300MM. (Ref. TASK 38-31-63-400-001).
1EFF : ALL 1 38-31-61Page 410 1 1 May 01/05R 1 1 1CES 1
**ON A/C 001-049, 051-099, 101-105,
Subtask 38-31-61-865-063
C. Make sure that this(these) circuit breaker(s) is(are) open, safetied and
tagged -------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 32MG A01 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 45MG A02 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 39MG A03 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 34MG A04 2001VU VACUUM TOILET SYSTEM/VACUUM SYS 35MG A06 2001VU VACUUM TOILET SYSTEM/VACUUM GEN 33MG A08
**ON A/C 106-149, 151-199, 201-299,
Subtask 38-31-61-865-063-A
C. Make sure that this(these) circuit breaker(s) is(are) open, safetied and
tagged -------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------2001VU VACUUM TOILET SYSTEM/LAVATORY POWER A 32MG A01 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 45MG A02 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER D 39MG A03 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER E 34MG A04 2001VU VACUUM TOILET SYSTEM/VACUUM SYS 35MG A06 2001VU VACUUM TOILET SYSTEM/VACUUM GEN 33MG A08
**ON A/C 301-399,
Subtask 38-31-61-865-063-B
C. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged
R 1EFF : 001-049, 051-099, 101-149, 151-199, 1 38-31-61Page 411 1201-299, 301-399, 1Aug 01/05 1 1 1CES 1
-------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------2001VU VACUUM TOILET SYSTEM/LAVATORY POWER A 32MG A01 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER L 45MG A02 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER D 39MG A03 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER E 34MG A04 2001VU VACUUM TOILET SYSTEM/VACUUM SYS 35MG A06 2001VU VACUUM TOILET SYSTEM/VACUUM GEN 33MG A08
**ON A/C ALL
4. Procedure
_________ (Ref. Fig. 401/TASK 38-31-61-991-001) R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 401-499,
Subtask 38-31-61-420-052
A. Installation of the Waste holding Tank 3300MM
(1)
Clean the component interface and/or the adjacent area.
(2)
Do an inspection of the component interface and/or the adjacent area.