 Connect the electrical connectors (4, 6, 7 and 8).

 


 Subtask 38-31-12-710-050
 B. Operate the toilet and make sure that it flushes corrcetly (Ref. TASK 38-31-00-710-009).
 5. Close-up
________ Subtask 38-31-12-410-050
 A. Close Access
 (1)
 Make sure that the work area is clean and clear of tool(s) and other items.

 (2)
 Install the toilet shroud (Ref. TASK 25-45-22-400-001).


 (3) Close the lavatory door. Subtask 38-31-12-862-050
 B. De-energize the ground service network
 (Ref. TASK 24-42-00-862-001).

 

 LIMIT SWITCH - WASTE PANEL DOOR (44MG) - REMOVAL/INSTALLATION
_____________________________________________________________
 TASK 38-31-13-000-001
 Removal of the Waste Service-Panel Door Limit-Switch (44MG)
 1.
 Reason for the Job

__________________
 Self Explanatory


 2.
 Job Set-up Information


______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------
REFERENCE  QTY DESIGNATION
 -------------------------------------------------------------------------------
No specific  blanking caps
R  No specific circuit breaker(s) safety clip(s) No specific warning notices No specific access platform 3 m (9 ft. 10 in.)
 B. Referenced Information
 -------------------------------------------------------------------------------
REFERENCE  DESIGNATION
 -------------------------------------------------------------------------------
24-42-00-861-001  Energize the Ground Service Network from the External Power 52-30-00-860-001 Open the FWD or AFT Cargo-Compartment Door with the Yellow Electric Pump 38-31-13-991-001 Fig. 401
 3. Job Set-up
__________
 Subtask 38-31-13-861-050

 A. Energize the ground service network
 (Ref. TASK 24-42-00-861-001)

 


R **ON A/C 001-049, 051-099, 101-105,

 Subtask 38-31-13-865-053
 B. Open, safety and tag this(these) circuit breaker(s): -------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 32MG A01 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 45MG A02 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 39MG A03 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 34MG A04 2001VU VACUUM TOILET SYSTEM/VACUUM SYS 35MG A06 2001VU VACUUM TOILET SYSTEM/VACUUM GEN 33MG A08

R **ON A/C 106-149, 151-199, 201-299,
 Subtask 38-31-13-865-053-A
 B. Open, safety and tag this(these) circuit breaker(s): -------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------2001VU VACUUM TOILET SYSTEM/LAVATORY POWER A 32MG A01 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 45MG A02 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER D 39MG A03 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER E 34MG A04 2001VU VACUUM TOILET SYSTEM/VACUUM SYS 35MG A06 2001VU VACUUM TOILET SYSTEM/VACUUM GEN 33MG A08
 **ON A/C 301-399,
 Subtask 38-31-13-865-053-B
 B. Open, safety and tag this(these) circuit breaker(s): -------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------
2001VU VACUUM TOILET SYSTEM/LAVATORY POWER A 32MG A01 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER L 45MG A02 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER D 39MG A03 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER E 34MG A04 2001VU VACUUM TOILET SYSTEM/VACUUM SYS 35MG A06 2001VU VACUUM TOILET SYSTEM/VACUUM GEN 33MG A08

 **ON A/C ALL


 Subtask 38-31-13-010-051
 C. Get Access
 (1)
 Put the access platform below the waste service panel.

 (2)
 Open the waste service-panel door 171AR.

 (3)
 Put the warning notices in position to tell persons not to operate the toilets.

 (4)
 Open the AFT cargo-compartment door (Ref. TASK 52-30-00-860-001).

 (5)
 Open the access door 162DW.

 (6)
 Set the CARGO COMP light-switch 8LU on the service panel 2024VU to the ON position.


 4. Procedure
_________
 (Ref. Fig. 401/TASK 38-31-13-991-001) Subtask 38-31-13-020-050
 A. Removal of the Waste Service-Panel Door-Switch 44MG
 (1)
 Disconnect the electrical connector 44MG-A (1).
 
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM WATER/WASTE 2(45)