 1EFF : ALL 1 38-31-36Page 403 1 1 Feb 01/05R 1 1 1CES 1


 Motor Start Relay Figure 401/TASK 38-31-36-991-001
 1EFF : 1 1R 1CES  ALL  1 11 1 38-31-36 Page 404 Aug 01/03


 TASK 38-31-36-400-001


 Installation of the Motor Start Relay (36MG)
 1. Reason for the Job
__________________
 Self Explanatory
 2. Job Set-up Information
______________________
 A. Fixtures, Tools, Test and Support Equipment
 -------------------------------------------------------------------------------
REFERENCE QTY DESIGNATION
 -------------------------------------------------------------------------------
R No specific Torque Wrench : range 0.00 to 1.20 m.daN R (0.00 to 9.00 lbf.ft) R
 B. Referenced Information
 -------------------------------------------------------------------------------
REFERENCE DESIGNATION
 -------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 24-42-00-862-001 De-energize the Ground Service Network Supplied from the External Power 25-55-12-400-001 Installation of the AFT Cargo Compartment Partition
 FR65 38-31-00-710-009 Operational Test of the Toilet Unit 38-31-00-740-001 BITE Test of the Vacuum Toilet System 52-30-00-860-002 Close the FWD or AFT Cargo-Compartment Door with the
 Yellow Electric Pump
 38-31-36-991-001 Fig. 401

 3. Job Set-up
__________
 Subtask 38-31-36-860-050
 A. Aircraft Maintenance Configuration
 (1) Make sure that the ground service network is energized from the external power (Ref. TASK 24-42-00-861-001).

 

R **ON A/C 001-049, 051-099, 101-105,

 Subtask 38-31-36-865-051
 B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and
 tagged -------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 32MG A01 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 45MG A02 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 39MG A03 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 34MG A04 2001VU VACUUM TOILET SYSTEM/VACUUM SYS 35MG A06 2001VU VACUUM TOILET SYSTEM/VACUUM GEN 33MG A08
R **ON A/C 106-149, 151-199, 201-299,
 Subtask 38-31-36-865-051-A
 B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and
 tagged -------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------2001VU VACUUM TOILET SYSTEM/LAVATORY POWER A 32MG A01 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 45MG A02 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER D 39MG A03 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER E 34MG A04 2001VU VACUUM TOILET SYSTEM/VACUUM SYS 35MG A06 2001VU VACUUM TOILET SYSTEM/VACUUM GEN 33MG A08
 **ON A/C 301-399,
 Subtask 38-31-36-865-051-B
 B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged


 -------------------------------------------------------------------------------
PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------2001VU VACUUM TOILET SYSTEM/LAVATORY POWER A 32MG A01 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER L 45MG A02 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER D 39MG A03 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER E 34MG A04 2001VU VACUUM TOILET SYSTEM/VACUUM SYS 35MG A06 2001VU VACUUM TOILET SYSTEM/VACUUM GEN 33MG A08
 **ON A/C ALL
 4. Procedure
_________ (Ref. Fig. 401/TASK 38-31-36-991-001) Subtask 38-31-36-420-050
 A. Installation of the Motor Start Relay 36MG
 (1)
 Clean the component interface and/or the adjacent area.

 (2)
 Do an inspection of the component interface and/or the adjacent area.

 (3)
 Put the motor start relay (14) and the brackets (3) and (15) in the correct position on the bracket (1).


 NOTE : The connector-plug and the contact-bolts L1 thru L3 and T1
____ thru T3 must have the same position as recorded in the removal.
 (4)
 Install the washers (4), the screws (5) and the spacer (2).

 (5)
 TORQUE the screws (5) to between 0.22 and 0.38 m.daN (19.46 and 33.62 lbf.in).

 (6)
 Put the cables (6) in position on the contact-bolts L1 thru L3 and T1 thru T3.


 CAUTION : REFER TO THE MATCH MARKS MADE DURING THE REMOVAL WHEN YOU
_______ CONNECT THE ELECTRICAL WIRES. INCORRECT CONNECTION OF THE WIRES WILL CAUSE DAMAGE TO EQUIPMENT.
 