Subtask 38-31-19-614-051
E. Release the pressure from the potable water system (Ref. TASK 38-10-00-614-002).
5. Close-up
________ Subtask 38-31-19-862-050
A. De-energize the ground service network
(Ref. TASK 24-42-00-862-001).
CONTROLLER - VACUUM SYSTEM (31MG) - REMOVAL/INSTALLATION
________________________________________________________
TASK 38-31-34-000-001
Removal of the Vacuum System Controller 31MG
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------
REFERENCE QTY DESIGNATION
-------------------------------------------------------------------------------
No specific circuit breaker(s) safety clip(s)
No specific access platform 1.0 m (3 ft. 3 in.)
B. Referenced Information
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 52-30-00-860-001 Open the FWD or AFT Cargo-Compartment Door with the Yellow Electric Pump 38-31-34-991-001 Fig. 401
3. Job Set-up
__________
Subtask 38-31-34-861-050
A. Energize the ground service network
(Ref. TASK 24-42-00-861-001).
R **ON A/C 001-049, 051-099, 101-105,
Subtask 38-31-34-865-056
B. Open, safety and tag this(these) circuit breaker(s):
R 1EFF : 001-049, 051-099, 101-105, 151-199, 1 38-31-34Page 401 1201-299, 1May 01/05 1 1 1CES 1
-------------------------------------------------------------------------------
PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 32MG A01 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 45MG A02 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 39MG A03 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 34MG A04 2001VU VACUUM TOILET SYSTEM/VACUUM SYS 35MG A06 2001VU VACUUM TOILET SYSTEM/VACUUM GEN 33MG A08
**ON A/C 151-199, 201-299,
Subtask 38-31-34-865-056-A
B. Open, safety and tag this(these) circuit breaker(s): -------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------2001VU VACUUM TOILET SYSTEM/LAVATORY POWER A 32MG A01 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER 45MG A02 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER D 39MG A03 2001VU VACUUM TOILET SYSTEM/LAVATORY POWER E 34MG A04 2001VU VACUUM TOILET SYSTEM/VACUUM SYS 35MG A06 2001VU VACUUM TOILET SYSTEM/VACUUM GEN 33MG A08
R **ON A/C 001-049, 051-099, 101-105, 221-221, 224-224, 228-228,
Subtask 38-31-34-010-050
C. Get Access
(1)
Put the access platform in position.
(2)
Open the BULK cargo-compartment door.
(3)
Remove the aft corner section and the access panel 162GW.
R 1EFF : 001-049, 051-099, 101-105, 151-199, 1 38-31-34Page 402 1201-299, 1May 01/05 1 1 1CES 1 **ON A/C 151-199, 201-220, 222-223, 225-227, 229-299,
Subtask 38-31-34-010-050-A
C. Get Access
(1)
Put the access platform in position.
(2)
Open the AFT cargo-compartment door (Ref. TASK 52-30-00-860-001).
(3) Remove the access panel 162BW. R **ON A/C 001-049, 051-099, 101-105, 151-199, 201-299,
4. Procedure
_________
(Ref. Fig. 401/TASK 38-31-34-991-001)
Subtask 38-31-34-020-050
A. Removal of the Vacuum System Controller 31MG
(1)
Loosen the fastener (1).
(2)
Remove the vacuum controller (2).
R 1EFF : 001-049, 051-099, 101-105, 151-199, 1 38-31-34Page 403 1201-299, 1May 01/05 1 1 1CES 1
Vacuum System Controller
Figure 401/TASK 38-31-34-991-001
R 1EFF : 001-049, 051-099, 101-105, 151-199, 1 38-31-34Page 404 1201-299, 1May 01/05 1 1 1CES 1
TASK 38-31-34-400-001
Installation of the Vacuum System Controller 31MG
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM WATER/WASTE 2(50)