(2)
Do an inspection of the component interface and/or the adjacent area.
Subtask 33-41-15-420-051-A
B. Installation of the Tail Navigation Light
(1) Remove the blanking caps from the electrical connectors (5) and (6).
(2) Make sure that the electrical connectors are clean and in the correct condition.
R R R (3) Connect the electrical connectors (5) and (6) to the tail navigation light (3).
(4) Put the tail navigation light (3) in position on the APU exhaust access-fairing (4).
(5) Install the the screws (1) and the washers (2).
(6) Clean the outer side of the tail navigation light (3) with a, MISCELLANEOUS (Material No. 19-003).
(7) Apply the SEALANTS (Material No. 09-023), or the SEALANTS (Material No. 09-019) to all sides of the mating flange of the tail navigation light (3), the washers (2) and the screws (1).
NOTE : The tack free time of the SEALANTS (Material No. 09-023) is 24____ hours and the cure time is 72 hours at 25 deg.C (77.00 deg.F). The tack free time of the SEALANTS (Material No. 09-019) is 10 hours and the cure time is 24 hours at 25 deg.C (77.00 deg.F).
Subtask 33-41-15-865-052
C. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s): 1LA, 2LA, 10LV, 1KD, 2KD.
Subtask 33-41-15-861-050
D. Energize the aircraft electrical circuits (Ref. TASK 24-41-00-861-002).
Subtask 33-41-15-710-050
R R E. Do the operational test of the tail navigation lights (Ref. TASK 33-41-00-710-001) and (Ref. TASK 33-48-00-710-002).
5. Close-up
________ Subtask 33-41-15-942-050
A. Close Access
(1) Make sure that the work area is clean and clear of tool(s) and other items.
(2) Remove the access platform(s). Subtask 33-41-15-862-050
B. De-energize the aircraft electrical circuits (Ref. TASK 24-41-00-862-002).
1EFF : ALL 1 33-41-15Page 407 1 1 Aug 01/04R 1 1 1CES 1
R TASK 33-41-15-000-002
R Removal of the Lamp(s) of the Tail Navigation Light 15LA
R WARNING : MAKE SURE THAT ALL THE CIRCUITS IN MAINTENANCE ARE ISOLATED BEFORE_______
R YOU SUPPLY ELECTRICAL POWER TO THE AIRCRAFT.
R 1. Reason for the Job__________________
R Self Explanatory
R 2. Job Set-up Information______________________
R A. Fixtures, Tools, Test and Support Equipment
R -------------------------------------------------------------------------------
R REFERENCE QTY DESIGNATION
R -------------------------------------------------------------------------------
R No specific circuit breaker(s) safety clip(s)
R No specific 1 ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE
R B. Referenced Information
R -------------------------------------------------------------------------------
R REFERENCE DESIGNATION
R -------------------------------------------------------------------------------
R 33-41-15-991-002 Fig. 402
R 3. Job Set-up__________
R Subtask 33-41-15-865-053
R A. Open, safety and tag this(these) circuit breaker(s):
R -------------------------------------------------------------------------------
R PANEL DESIGNATION IDENT. LOCATION
R -------------------------------------------------------------------------------
R 121VU APU/APU/CTL 2KD L42
R 121VU APU/ECB/SPLY 1KD L41
R 122VU LIGHTING/EXT LT/NAV1/AND LOGO/LT 1LA T03