Do the EIS start procedure (Upper ECAM DU and lower ECAM DU only) (Ref. TASK 31-60-00-860-001).
4. Procedure
_________ Subtask 21-63-00-710-053
A. Operational Test of the Zone-Controller (Back Up Switching) via CFDS/MCDU
-------------------------------------------------------------------------------ACTION RESULT -------------------------------------------------------------------------------
1. On the panel 122VU: - open the circuit breakers 1HK and 3HK. On the ECAM upper display unit, (afterapprx. 60 seconds):- the warning message COND ZONE REGUL FAULT comes on.
2. On the ECAM control panel 11VU:
- push one of the two CLR pushbutton switches. - the warning message goes off.
On the ECAM lower display unit: - the status message CAB ZONE AT FIXED TEMP comes on.
3. On the panel 122vu: - close the circuit breakers 1HK and 3HK. On the ECAM lower display unit:- the status message goes off.
On the ECAM upper display unit: - the warning message COND HOT AIR FAULT may show.
R 1EFF : 001-049, 051-099, 101-149, 151-199, 1 21-63-00Page 509 1201-299, 301-399, 1Aug 01/05 1 1 1CES 1
5. Close-up
________ Subtask 21-63-00-860-051
A. Put the aircraft back to its initial configuration.
(1)
Do the EIS stop procedure
(Ref. TASK 31-60-00-860-002).
(2)
De-energize the aircraft electrical circuits (Ref. TASK 24-41-00-862-002).
R 1EFF : 001-049, 051-099, 101-149, 151-199, 1 21-63-00Page 510 1201-299, 301-399, 1Aug 01/05 1 1 1CES 1 **ON A/C ALL
TASK 21-63-00-710-005
Operational Test of the Trim Air Check-Valves
1.
Reason for the Job
__________________
Referenced from TSM
2.
Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
12-33-21-618-001 Pre-conditioning through the HP Ground Connection 12-33-21-618-001 Pre-conditioning with the APU 24-41-00-861-002 Energize the Aircraft Electrical Circuits from the
External Power 24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied
from the External Power
31-60-00-860-001 EIS Start Procedure
31-60-00-860-002 EIS Stop Procedure
3. Job Set-up
__________
Subtask 21-63-00-865-073
A. Make sure that this(these) circuit breaker(s) is(are) closed:
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------
R **ON A/C 401-499,
49VU AIR COND/TEMP CTL/SYS 1 CHAN B/28VDC 52HH D08 R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 301-399,
122VU AIR COND/ZONE TEMP CTL/28VDC/SYS2 4HK V20
-------------------------------------------------------------------------------
R PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------122VU AIR COND/ZONE TEMP CTL/28VDC/SYS1 3HK V19 122VU AIR COND/ZONE TEMP CTL/115VAC/SYS2 2HK V18 122VU AIR COND/ZONE TEMP CTL/115VAC/SYS1 1HK V17 122VU AIR COND/PACK TEMP/CTL SYS1/2/115VAC 21HH W22 122VU AIR COND/PACK TEMP/CTL SYS1/2/28VDC 23HH W21 122VU AIR COND/PACK TEMP/CTL SYS1/1/115VAC 1HH X22 122VU AIR COND/PACK TEMP/CTL SYS1/1/28VDC 3HH X21 122VU AIR COND/PACK TEMP CTL SYS2/2/28VDC 24HH Y21 122VU AIR COND/PACK TEMP CTL SYS2/2/115VAC 22HH Y20
R **ON A/C 001-049, 051-099, 101-105, 151-199, 201-299, 301-302,
R 122VU AIR COND/PACK TEMP CTL SYS2/1/28VDC 4HH Y19
R **ON A/C 001-049, 051-099, 101-149, 151-199, 201-299, 301-399,
R 122VU AIR COND/PACK TEMP CTL SYS2/1/115VAC 2HH Y18
R **ON A/C 106-149, 303-399,
R 122VU 4HH Y19
R **ON A/C 401-499,
R R R R R R R 122VU AIR COND/TEMP CTL SYS 2/CHAN A/115VAC 122VU AIR COND/TEMP CTL SYS 2/CHAN A/28VDC 122VU AIR COND/TEMP CTL SYS 1/CHAN A/115VAC 122VU AIR COND/TEMP CTL SYS 1/CHAN A/28VDC 122VU AIR COND/TEMP CTL SYS 2/CHAN B/28VDC 122VU AIR COND/TEMP CTL SYS 2/CHAN B/115VAC 122VU AIR COND/TEMP CTL SYS 1/CHAN B/115VAC 53HH 55HH 49HH 51HH 56HH 54HH 50HH W22 W21 X22 X21 Y21 Y20Y18
**ON A/C ALL
Subtask 21-63-00-860-056
B. Aircraft Maintenance Configuration