5. Close-up
________ Subtask 38-14-46-410-050
A. Close Access
(1)
Make sure that the work area is clean and clear of tool(s) and other items.
(2)
Install the access panels 162DW, 161DW.
(3)
Install the insulation (9) and (8) around the fill/drain valve 16MA. (Ref. Fig. 401/TASK 38-14-46-991-001)
CAUTION : MAKE SURE THAT THE INSULATION DOES NOT STOP THE OPERATION
_______
OF THE VALVE.
(a) Close the AFT cargo-compartment door (Ref. TASK 52-30-00-860-002).
(b) Remove the access platform(s). Subtask 38-14-46-862-050
B. De-energize the ground service network
(Ref. TASK 24-42-00-862-001).
R 1EFF : 001-049, 051-099, 101-149, 201-299, 1 38-14-46Page 408 1 1 May 01/05 1 1 1CES 1 CONTROL CABLE - FILL/DRAIN VALVE (3254MM) - REMOVAL/INSTALLATION
________________________________________________________________
TASK 38-14-47-000-001
Removal of the Control Cable 3254MM
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------
REFERENCE QTY DESIGNATION
-------------------------------------------------------------------------------
No specific circuit breaker(s) safety clip(s)
No specific nonmetallic scraper
No specific access platform 2 m (6 ft. 7 in.)
B. Referenced Information
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
24-42-00-861-001 Energize the Ground Service Network from the External Power 52-30-00-860-001 Open the FWD or AFT Cargo-Compartment Door with the Yellow Electric Pump
**ON A/C 001-049, 051-099, 101-149, 201-299,
38-14-47-991-001 Fig. 401 R **ON A/C 151-199, 301-399, 401-499,
38-14-47-991-001-A Fig. 401A **ON A/C ALL
3. Job Set-up
__________
Subtask 38-14-47-861-051
A. Energize the ground service network
(Ref. TASK 24-42-00-861-001).
Subtask 38-14-47-010-050
B. Get Access
(1)
Put the access platform in position at Zone 171.
(2)
Open the access panel 171AL.
(3)
Open the AFT cargo-compartment door (Ref. TASK 52-30-00-860-001).
(4) Remove the access panel 161DW.
**ON A/C 001-049, 051-099, 101-149, 201-299,
Subtask 38-14-47-865-050-A
C. Open, safety and tag this(these) circuit breaker(s): -------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------
2000VU WATER SYS - QUANT IND 1MA B01
R **ON A/C 151-199, 301-399, 401-499,
Subtask 38-14-47-865-050-B
C. Open, safety and tag this(these) circuit breaker(s): -------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------
2001VU WATER SYS - QUANT IND 1MA B06
**ON A/C ALL
4. Procedure
_________
**ON A/C 001-049, 051-099, 101-149, 201-299,
(Ref. Fig. 401/TASK 38-14-47-991-001) R **ON A/C 151-199, 301-399, 401-499,
(Ref. Fig. 401A/TASK 38-14-47-991-001-A)
**ON A/C ALL
Subtask 38-14-47-020-050
A. Removal of the Control Cable 3254MM
(1)
Remove and discard the cotter pin (9).
(2)
Remove the washer (8) and the pin (7).
(3)
Loosen the nut (10) but do not remove it.
(4)
Turn the sliding end (11) clockwise and remove it from the cable (3).
(5)
Loosen the nut (1) at the control handle assembly (12).
(6)
Remove the sealant from around the flange of the control handle (12) with a nonmetallic scraper.
(7) 中国航空网 www.aero.cn 航空翻译 www.aviation.cn 本文链接地址:A320飞机维护手册 AMM WATER/WASTE 1(89)