At the service panel 2023VU:
-
the quantity indicator 6MA shows 1/2full.
On the FAP 120RH/miscellaneous panel WATER AND WASTE 124RH:
-
the quantity indicator shows 50% full.
On the FAP 120RH/miscellaneous panelWATER AND WASTE 124RH:
-there is no indication.
On the FAP 120RH/miscellaneous panelWATER AND WASTE 124RH:
-
the quantity indicator shows 50%full.
At the service panel 2023VU:
-
the quantity indicator 6MA shows 3/4full.
On the FAP 120RH/miscellaneous panel WATER AND WASTE 124RH:
-
the quantity indicator shows 75% full.
On the FAP 120RH/miscellaneous panelWATER AND WASTE 124RH:
-there is no indication.
On the FAP 120RH/miscellaneous panelWATER AND WASTE 124RH:
R 1EFF : 151-199, 301-399, 401-499, 1 38-13-00Page 505 1 1 Aug 01/05 1 1 1CES 1
-------------------------------------------------------------------------------ACTION RESULT -------------------------------------------------------------------------------
- push and hold the membrane switch 'IND ON'.
R R R 10. At the service panel 2023VU: - fill the potable water tank with 220 l (58.12 USgal) of water.
11. At the service panel 2023VU:
-push and hold the door limit switch 5MA.
12. At the FAP 120RH/miscellaneous panel WATER AND WASTE 124RH:
-push and hold the membrane switch 'IND ON'.
**ON A/C ALL
5. Close-up
________
Subtask 38-13-00-080-050
-
the quantity indicator shows 75%full.
At the service panel 2023VU:
-
the motorized fill/overflow/drain valve 8MA closes.
-
the TANK FULL control light comes on.
-
the quantity indicator 6MA shows full.
-
the fill and drain handle goes back to the NORMAL position.
On the FAP 120RH/miscellaneous panel WATER AND WASTE 124RH:
-
the quantity indicator shows 100% full.
At the service panel 2023VU:
-
the TANK FULL control light goes off.
On the FAP 120RH/miscellaneous panel WATER AND WASTE 124RH:
-there is no indication.
On the FAP 120RH/miscellaneous panelWATER AND WASTE 124RH:
-the quantity indicator shows 100%full.
A. Disconnect the water service vehicle. Subtask 38-13-00-862-050
B. De-energize the ground service network the aircraft electrical network (Ref. TASK 24-42-00-862-001).
Subtask 38-13-00-410-050
C. Close the service panel 171AL.
1EFF : ALL 1 38-13-00Page 507 1 1 Feb 01/00R 1 1 1CES 1
TASK 38-13-00-710-002
Operational Test of the Door Limit Switch 5MA
1.
Reason for the Job
__________________
Self Explanatory
2.
Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------
REFERENCE QTY DESIGNATION
-------------------------------------------------------------------------------
R No specific 1 ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE
B. Referenced Information
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
12-24-38-680-001 Draining of the Potable Water System (with Electrical Power) 24-42-00-861-001 Energize the Ground Service Network from the External Power 24-42-00-862-001 De-energize the Ground Service Network Supplied from the External Power
3. Job Set-up
__________
Subtask 38-13-00-861-051
A. Energize the ground service network
aircraft electrical circuits (Ref. TASK 24-42-00-861-001).
Subtask 38-13-00-865-051
B. Make sure that this(these) circuit breaker(s) is(are) closed:
-1MA, 1MP
Subtask 38-13-00-010-051
C. Get Access
(1) Put an ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position below the potable water service-panel.
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM WATER/WASTE 1(57)