R  (1) Get access to the passenger cabin. 
R  (2) Open the door of the lavatory. 
R  (3) Open the sanitary cabinet door. 
R  (4) Remove the toilet shroud (Ref. TASK 25-45-22-000-001) 
R  (5) Put a CONTAINER 1 L (1/4 USGAL) below the shutoff valve (12). 
R
 **ON A/C ALL
 4. Procedure_________
 **ON A/C 001-003, 051-052,
 (Ref. Fig. 401/TASK 38-12-14-991-001)

 

R Shutoff Valve Figure 401/TASK 38-12-14-991-001
 1EFF : 001-003, 051-052, 1 38-12-14Page 404 1 1 Aug 01/05 1 1 1CES 1


R Shutoff Valve Figure 401A/TASK 38-12-14-991-001-A
R 1EFF : 004-049, 053-099, 101-149, 151-199, 1 38-12-14Page 405 1201-299, 301-399, 401-499, 1Aug 01/05 1 1 1CES 1


R **ON A/C 004-049, 053-099, 101-149, 151-199, 201-299, 301-399, 401-499,

 (Ref. Fig. 401A/TASK 38-12-14-991-001-A) 
R  **ON A/C 001-003, 051-052, 
R  Subtask 38-12-14-020-050-B 
R  A. Removal of the Shutoff Valve (4) 
R  (Ref. Fig. 401/TASK 38-12-14-991-001) 
R  (1) Disconnect the pipe connections (3). 
R  (2) Remove the nuts (6) and the washers (5). 
R  (3) Remove the bolts (1) and the washers (2). 
R  (4) Remove the shutoff valve (4) from the bracket. 
R  **ON A/C 004-049, 053-099, 101-149, 151-199, 201-299, 301-399, 401-499,
 Subtask 38-12-14-020-050 
R  A. Removal of the Shutoff Valve (12) 

R  (Ref. Fig. 401A/TASK 38-12-14-991-001-A) 

R  (1) Disconnect the pipe connections (8). 
R  (2) Remove the counter sink screws (4) and the counter sink washers (5). 
R  (3) Remove the shutoff valve (12) together with the bracket (9). 
R  (4) If necessary remove the bolts (11) the washers (10) and the bracket 
R  (9) from the shutoff valve (12). 
R  (5) If necessary remove the control rod (2) 
R  (a) Remove the nuts (13) the washers (14) and the counter sink screws 
R  (1).

 

R (b) remove the control rod (2) together with the brackets (3) and R (6). R
R 1EFF : 004-049, 053-099, 101-149, 151-199, 1 38-12-14Page 407 1201-299, 301-399, 401-499, 1Aug 01/05 1 1 1CES 1

 **ON A/C ALL


 TASK 38-12-14-400-001
 Installation of a Potable Water-Shutoff Valve
 NOTE : The installation of the shutoff valve is the same in all the lavatories.
____
 1. Reason for the Job
__________________
 Self Explanatory
 2. Job Set-up Information
______________________
 A. Referenced Information
 -------------------------------------------------------------------------------
REFERENCE DESIGNATION
 -------------------------------------------------------------------------------
12-15-38-613-001 Fill the Potable Water Tank System (Aircraft Electrical Power Available) 24-41-00-861-002 Energize the Aircraft Electrical Circuits from the External Power 24-41-00-862-002 De-energize the Aircraft Electrical Circuits Supplied from the External Power R 25-45-22-400-001 Installation of the Toilet Shroud and the Seat 38-10-00-614-001 Pressurization of the Potable Water System from a
 Ground Air Supply 38-10-00-614-002 Depressurization of the Potable Water System 38-10-00-670-002 Sterilization of Water Tank and Distribution System
 **ON A/C 001-003, 051-052,
 38-12-14-991-001 Fig. 401
R **ON A/C 004-049, 053-099, 101-149, 151-199, 201-299, 301-399, 401-499,
 38-12-14-991-001-A Fig. 401A **ON A/C ALL


 3. Job Set-up
__________
 Subtask 38-12-14-860-050
 A. Aircraft Maintenance Configuration
 (1)
 Make sure that the aircraft electrical circuits are energized (Ref. TASK 24-41-00-861-002).

 (2)
 Make sure that the potable water system is depressurized (Ref. TASK 38-10-00-614-002)

 (3)
 Make sure that the parts retained from the removed component are clean and in the correct condition.


 **ON A/C 001-049, 051-099, 101-149, 201-299,
 Subtask 38-12-14-865-054-B
 B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and
 tagged -------------------------------------------------------------------------------PANEL SERVICE IDENT. LOCATION -------------------------------------------------------------------------------
2000VU WATER SYS - QUANT IND 1MA B01 2001VU WATER SYS - DRAIN 1MP B05

R **ON A/C 151-199, 301-399, 401-499,
 Subtask 38-12-14-865-054-A
 B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and
 