(2)
Remove the trailing edge access panels:
334BB, 334DB, 334FB, 334HB.
344BB, 344DB, 344FB, 344HB.
(Ref. TASK 55-13-11-000-001)
(3) Remove the elevator leading edge access panels
335AB, 335BB, 335CB, 335DB.
345AB, 345BB, 345CB, 345DB.
(Ref. TASK 55-22-11-000-001)
_________
4. Procedure
Subtask 05-23-30-210-054
A. Inspection
(1)
Do a general visual inspection of the elevator.
(2)
Make sure that there are no signs of corrosion, cracks or damage.
(3)
Make sure that all the installations (wiring, ducting, piping) are attached correctly.
5. Close-up
________ Subtask 05-23-30-410-054
A. Close Access
(1)
Install the trailing edge access panels
334BB, 334DB, 334FB, 334HB.
344BB, 344DB, 344FB, 344HB.
(Ref. TASK 55-13-11-400-001)
(2)
Install the elevator leading edge access panels
335AB, 335BB, 335CB, 335DB.
345AB, 345BB, 345CB, 345DB.
(Ref. TASK 55-22-11-400-001)
(3)
Remove the access platform(s).
TASK 05-23-30-200-007
Zonal Inspection of the Trailing Edge of the Trimmable Horizontal Stabilizer
1. Reason for the Job
__________________
Refer to the MPD TASK: ZL-334-02
2. Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific access platform 4 m (13 ft. 1 in.)
B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
55-13-11-000-001 Removal of the THS Trailing Edge Access Panels 55-13-11-400-001 Installation of the THS Trailing Edge Access Panels
3. Job Set-up
__________ Subtask 05-23-30-010-056
A. Get Access
(1)
Put an access platform in position.
(2)
Remove the trailing edge access panels
334AT, 334BT, 334CT,
334DT, 334AB, 334BB,
334CB, 334DB, 334EB,
334FB, 334GB, 334HB,
344AT, 344BT, 344CT,
344DT, 344AB, 344BB,
344CB, 344DB, 344EB,
344FB, 344GB, 344HB,
(Ref. TASK 55-13-11-000-001)
4. Procedure
_________
Subtask 05-23-30-210-056
A. Inspection
(1)
Do a general visual inspection of the trailing edge of the trimmable horizontal stabilizer.
(2)
Make sure that there are no signs of corrosion, cracks or damage.
(3)
Make sure that all the installations (wiring, ducting, piping) are attached correctly.
5. Close-up
________
Subtask 05-23-30-410-056
A. Close Access
(1)
Install the trailing edge access panels:
334AT, 334BT, 334CT,
334DT, 334AB, 334BB,
334CB, 334DB, 334EB,
334FB, 334GB, 334HB.
344AT, 344BT, 344CT,
344DT, 344AB, 344BB,
344CB, 344DB, 344EB,
344FB, 344GB, 344HB,
(Ref. TASK 55-13-11-400-001)
(2)
Remove the access platform(s).
ZONAL INSPECTION : POWER PLANT, NACELLES AND PYLONS - INSPECTION/CHECK
______________________________________________________________________
TASK 05-24-00-200-001
Zonal Inspection as far as Visible from the Ground of the Power Plant, the Nacelles and the Pylons
1. Reason for the Job
__________________
R R Self Explanatory
2.
Job Set-up Information
______________________
Not Applicable
3.
Job Set-up
__________
Subtask 05-24-00-869-050
A. Not Applicable
4. Procedure
_________
Subtask 05-24-00-210-050
A. Inspection
(1)
Do a general visual inspection of the power plant, the nacelles and the pylons from the ground during the aircraft walkaround.
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM 时间限制/维护检查 3(65)