4. Procedure
_________ Subtask 05-21-40-210-051
A. Inspection
(1)
Do a general visual inspection of the pressurized zone under the cabin floor.
(2)
Make sure that there are no signs of corrosion, cracks or damage.
(3)
Make sure that all the installations (wiring, ducting, piping) are attached correctly.
NOTE : Lift the insulation blankets sufficiently to complete a
____ correct general visual inspection as necessary.
5. Close-up
________
Subtask 05-21-40-410-051
A. Close Access
(1) Install the floor panels: 241EF, 241FF, 241GF, 241HF, 241JF, 241KF, 241LF, 241MF, 242FF, 242GF, 242HF, 242KF, 242LF, 242MF, in the passenger compartment. (Ref. TASK 53-32-12-400-002)
TASK 05-21-40-200-003
Zonal Inspection as far as visible from the Ground of the Main Gear Well and the Hydraulics Compartment (Zones 147 and 148)
1. Reason for the Job
__________________
R R Self Explanatory
2. Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
32-12-00-010-001 Open the Main Gear Doors for Access
32-12-00-410-001 Close the Main Gear Doors after Access
3. Job Set-up
__________
Subtask 05-21-40-010-052
A. Get Access
(1) Open the main landing gear doors
734, 744, (Ref. TASK 32-12-00-010-001).
4. Procedure
_________
Subtask 05-21-40-210-052
A. Inspection
(1)
Do a general visual inspection of the main gear well and the hydraulics compartment from the ground (Zones 147 and 148).
(2)
Make sure that there are no signs of corrosion, cracks or damage.
(3)
Make sure that all the installations (wiring, ducting, piping) are attached correctly.
5. Close-up
________
Subtask 05-21-40-410-052
A. Close Access
(1) Close the main landing gear doors
734, 744 , (Ref. TASK 32-12-00-410-001).
INTENTIONALLY BLANK
R 1 1
05-21-40Page 606
1 1 Nov 01/03 1 1 1CES 1
TASK 05-21-40-200-004
Zonal Inspection of the Main Gear Well and the Hydraulics Compartment (Zones 147 and 148)
1. Reason for the Job
__________________
Refer to the MPD TASK: ZL-147-02
2. Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific access platform 2 m (6 ft. 7 in.)
B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
32-12-00-010-001 Open the Main Gear Doors for Access 32-12-00-410-001 Close the Main Gear Doors after Access
3. Job Set-up
__________ Subtask 05-21-40-010-053
A. Get Access
(1)
Put an access platform in position at the zones 147 and 148.
(2)
Open the main landing gear doors
734, 744 , (Ref. TASK 32-12-00-010-001).
4. Procedure
_________
Subtask 05-21-40-210-053
A. Inspection
(1)
Do a general visual inspection of the main gear well and the hydraulics compartment (Zones 147 and 148).
(2)
Make sure that there are no signs of corrosion, cracks or damage.
(3)
Make sure that all the installations (wiring, ducting, piping) are attached correctly.
5. Close-up
________ Subtask 05-21-40-410-053
A. Close Access
(1)
Close the main landing gear doors
734, 744 , (Ref. TASK 32-12-00-410-001).
(2)
Remove the access platform(s).