(2)
Open the access door 314AR.
(Ref. Fig. 601/TASK 05-23-10-991-001)
4. Procedure
_________
Subtask 05-23-10-210-051
A. Inspection
(1)
Do a general visual inspection of the air intake area of the APU on the tail cone (Zones 313 and 314).
(2)
Make sure that there are no signs of corrosion, cracks or damage.
(3)
Make sure that all the installations (wiring, ducting, piping) are attached correctly.
5. Close-up
________ Subtask 05-23-10-410-051
A. Close Access
(1)
Close the access door 314AR.
(2)
Remove the access platform(s).
TASK 05-23-10-200-003
R Zonal Inspection of Tail Cone APU and Accessory Compartment
1.
Reason for the Job
__________________
Refer to the MPD TASK: ZL-315-01
2.
Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific access platform 2.50 m (8 ft. 2 in.)
B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
52-41-00-010-001 Open the APU Doors for Access
52-41-00-410-001 Close the APU Doors after Access
3. Job Set-up
__________
Subtask 05-23-10-010-052
A. Get Access
(1)
Put an access platform in position at the zone 310.
(2)
Open the access doors:
315AL, 316AR.
(Ref. TASK 52-41-00-010-001)
4. Procedure
_________
Subtask 05-23-10-210-052
A. Inspection
R R R (1) Do a general visual inspection of the tail cone APU and accessory compartment.
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring, ducting, piping) are attached correctly.
5. Close-up________
Subtask 05-23-10-410-052
A. Close Access
(1) Close the access doors: 315AL, 316AR. (Ref. TASK 52-41-00-410-001)
(2) Remove the access platform(s).
TASK 05-23-10-200-004
Zonal Inspection of the APU Exhaust Area on the Tail Cone
1. Reason for the Job
__________________
Refer to the MPD TASK: ZL-317-01
2. Job Set-up Information
______________________
A. Fixtures, Tools, Test and Support Equipment
-------------------------------------------------------------------------------REFERENCE QTY DESIGNATION -------------------------------------------------------------------------------
No specific access platform 5 m (16 ft. 5 in.)
B. Referenced Information
-------------------------------------------------------------------------------REFERENCE DESIGNATION -------------------------------------------------------------------------------
52-41-18-000-001 Removal of the APU Exhaust Access-Fairing 317AL 52-41-18-400-001 Installation of the APU Exhaust Access-Fairing 317AL
3. Job Set-up
__________ Subtask 05-23-10-010-053
A. Get Access
(1)
Put an access platform in position at the zone 310.
(2)
Remove the access fairing 317AL.
(Ref. TASK 52-41-18-000-001)
4. Procedure
_________
Subtask 05-23-10-210-053
A. Inspection
(1)
Do a general visual inspection of the APU exhaust area on the tail cone.
(2)
Make sure that there are no signs of corrosion, cracks or damage.
(3)
Make sure that all the installations (wiring, ducting, piping) are attached correctly.
5. Close-up
________ Subtask 05-23-10-410-053
A. Close Access
(1)
Install the access fairing 317AL.
(Ref. TASK 52-41-18-400-001)
(2)
Remove the access platform(s).
ZONAL INSPECTION : VERTICAL STABILIZER AND RUDDER - INSPECTION/CHECK
____________________________________________________________________ TASK 05-23-20-200-001 Zonal Inspection of the Dorsal Fin
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM 时间限制/维护检查 3(58)