TASK 33-51-00-810-829
Failure of the Battery of EPSU 10WL
1. Possible Causes
_______________
- battery of EPSU 10WL
- EPSU (10WL)
2. Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
AMM 33-51-00-710-010 Operational Test of the Emergency Lights via MCDU AMM 33-51-00-710-011 Check Battery Capacity via MCDU AMM 33-51-38-000-001 Removal of the Emergency Power-Supply Unit (EPSU) AMM 33-51-38-000-002 Removal of the Battery of the Emergency Power-Supply
Unit
AMM 33-51-38-400-001 Installation of the Emergency Power-Supply Unit
(EPSU)
AMM 33-51-38-400-002 Installation of the Battery of the Emergency
Power-Supply Unit
3. Fault Confirmation
__________________
A. Do the operational test Check Battery Capacity via MCDU (Ref. AMM TASK 33-51-00-710-011).
4. Fault Isolation
_______________
A. If the test gives a different maintenance message, do the trouble shooting procedure related to the maintenance message.
B. If the operational test gives the maintenance message:
(1) BAT/EPSU(10WL)FWD L:
- do the Operational Test of the Emergency Lights via MCDU (Ref. AMM TASK 33-51-00-710-010).
C. If the test gives the maintenance message:
(1) BAT/EPSU(10WL)FWD L:
- replace the battery of EPSU 10WL (Ref. AMM TASK 33-51-38-000-002) and (Ref. AMM TASK 33-51-38-400-002).
(a) If the fault continues:
- replace the EPSU (10WL) (Ref. AMM TASK 33-51-38-000-001) and (Ref. AMM TASK 33-51-38-400-001).
「一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一1R EFF : 106-149, 301-399, 401-499, ∞∞33-51-00∞∞∞∞∞∞∞∞∞∞Page A224
Aug 01/05 CES D. Do the test given in para. 3.
5. Close-up
________
A. Put the aircraft back to its initial configuration.
TASK 33-51-00-810-830
Failure of EPSU 10WL to communicate with the CIDS
1. Possible Causes
_______________
- EPSU (10WL)
- wiring
2. Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
AMM 33-51-00-710-010 Operational Test of the Emergency Lights via MCDU AMM 33-51-38-000-001 Removal of the Emergency Power-Supply Unit (EPSU) AMM 33-51-38-400-001 Installation of the Emergency Power-Supply Unit
(EPSU)
ASM 33-51/01
3. Fault Confirmation
__________________
A. Do the operational test of the Emergency Lights via MCDU (Ref. AMM TASK 33-51-00-710-010).
4. Fault Isolation
_______________
A. If the test gives a different maintenance message, do the trouble shooting procedure related to the maintenance message.
B. If the operational test gives the maintenance message:
(1) EPSU(10WL)FWD L/DEU B(300RH1):
- replace the EPSU (10WL) (Ref. AMM TASK 33-51-38-000-001) and (Ref. AMM TASK 33-51-38-400-001).
(a) If the fault continues:
- do a check and repair the wiring between: EPSU 10WL pin -I and DEU-B 300RH1 pin B29. EPSU 10WL pin -P and DEU-B 300RH1 pin B31. EPSU 10WL pin X and DEU-B 300RH1 pin B30 (Ref. ASM 33-51/01).
C. Do the test given in para. 3.
5. Close-up
________
A. Put the aircraft back to its initial configuration.
「一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一一1R EFF : 106-149, 301-399, 401-499, ∞∞33-51-00∞∞∞∞∞∞∞∞∞∞Page A226
Aug 01/05 CES
TASK 33-51-00-810-831
Difference between System Test Requirements and Switch Position - EPSU 11WL
1. Possible Causes
_______________
- wiring
2. Job Set-up Information
______________________
A. Referenced Information
-------------------------------------------------------------------------------
REFERENCE DESIGNATION
-------------------------------------------------------------------------------
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320 Trouble Shooting Manual 排故手册 LIGHTS 灯光(127)