_______ MATERIALS ONLY WITH A GOOD SUPPLY OF AIR. OBEY THE MANUFACTURERS INSTRUCTIONS. PUT ON PROTECTIVE CLOTHING. DO NOT GET THEM IN YOUR MOUTH. DO NOT SMOKE. DO NOT BREATHE THE GAS. THESE MATERIALS ARE POISONOUS, FLAMMABLE AND SKIN IRRITANT. GET MEDICAL HELP IF YOUR SKIN OR EYES BECOME IRRITATED.
(1)
Clean the component interfaces and the adjacent areas with a MISCELLANEOUS (Material No. 19-003) made moist with CLEANING AGENTS (Material No. 11-026).
(2)
Make sure that the parts retained from the removed component are clean and in the correct condition.
(3)
Do an inspection of the component interface and/or the adjacent area.
(4)
Lubricate the new O-rings (1), (2) and (6) with FUELS (Material No. 01-001) or COMMON GREASE (Material No. 04-012).
Subtask 28-21-45-420-054
B. Installation of the Sequence Valve
(1)
Install the new O-ring (6) between the sequence valve (7) and the elbow (5).
(2)
Attach the sequence valve (7) to the elbow (5) with the bolts (4).
(3)
Install the new O-ring (2) between the elbow (5) and the mounting plate (9).
(4)
Attach the mounting plate (9) to the elbow (5) with the bolts (3).
R 1EFF : 001-049, 051-099, 101-149, 151-199, 1 28-21-45Page 408 1201-299, 401-499, 1Aug 01/05 1 1 1CES 1
(5)
Install the new O-ring (1) between the sequence valve assembly and the pump canister.
(6)
Attach the sequence valve assembly to the pump canister with the bolts (8).
(7)
Apply a layer of SEALANTS (Material No. 09-007) to the heads of the bolts (3), (4) and (8).
Subtask 28-21-45-410-051
C. Close Access
(1)
Make sure that the work area is clean and clear of tool(s) and other items.
(2)
Remove the HOOK-COVER (RIB2-SURGE DOORS) and carefully close the applicable surge door 540BZ, 640BZ.
(3)
Install the applicable access panel 540AB, 640AB (Ref. TASK 57-27-11-400-001).
Subtask 28-21-45-860-050
D. Preparation for Test
(Ref. Fig. 402/TASK 28-21-45-991-002)
(1)
Remove the applicable pressure switch (Ref. TASK 28-21-15-000-003):
-
for the sequence valve on the canister 1QM, remove the pressure switch 23QA
-
for the sequence valve on the canister 2QM, remove the pressure switch 27QA
-
for the sequence valve on the canister 3QM, remove the pressure switch 24QA
-
for the sequence valve on the canister 4QM, remove the pressure switch 28QA.
(2)
Install the ADAPTOR - SEQUENCE VALVE (99A28404000000) to the sealing valve where the pressure switch was attached. Use the pressure switch plug and O-rings.
(3)
Energize the aircraft electrical circuits (Ref. TASK 24-41-00-861-002).
R 1EFF : 001-049, 051-099, 101-149, 151-199, 1 28-21-45Page 409 1201-299, 401-499, 1Aug 01/05 1 1 1CES 1
Sequence Valves Test Equipment
Figure 402/TASK 28-21-45-991-002
R 1EFF : 001-049, 051-099, 101-149, 151-199, 1 28-21-45Page 410 1201-299, 401-499, 1Aug 01/05 1 1 1CES 1 Subtask 28-21-45-865-056
E. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s): 1QA, 2QA, 7QA, 8QA.
Subtask 28-21-45-650-053
F. Aircraft Maintenance Configuration
(1) Refuel the applicable wing tank to approximately 750 kg (1653.4665 lb) (Ref. TASK 12-11-28-650-003).
Subtask 28-21-45-720-050
G. Test of the Sequence Valve
(1) Do this test:
-------------------------------------------------------------------------------ACTION RESULT -------------------------------------------------------------------------------
1. On the panel 40VU:
-push the applicable TK PUMPS - the applicable P/BSW OFF legend goes pushbutton switch (P/BSW). off.
2. On the pressure gage: - make sure that the indication on the pressure gage becomes stable between
1.62 bar (23.50 psi) and 1.83 bar
(26.50 psi).
3. On the panel 40VU:
-push the applicable TK PUMPS - the applicable P/BSW OFF legend comes P/BSW. on.
R 1EFF : 001-049, 051-099, 101-149, 151-199, 1 28-21-45Page 411 1201-299, 401-499, 1Aug 01/05 1 1 1CES 1
5. Close-up
________ Subtask 28-21-45-865-057
A. Open, safety and tag this(these) circuit breaker(s):