Subtask 21-51-51-710-052
 E. Test
 (1)
 Do the pre-conditioning through the HP ground connector (Ref. TASK 12-33-21-618-001) or with the APU (Ref. TASK 12-33-21-618-001).
 (2)
 Do a leak check of the air ducts. NOTE : Minimum leakage is permitted. After the pack operates some
____ minutes, the leakage of air will reduce because the seals have their correct operating temperature.
 (3)
 Do a leak check of the sense line connections.
 NOTE : Leaks are not permitted.
____
 (4)
 After approx. 15 minutes stop the pre-conditioning (Ref. TASK 12-33-21-618-001) or (Ref. TASK 12-33-21-618-001).
 (5)
 Do the operational test of the pack temperature control system (Ref. TASK 21-61-00-710-001).
 5. Close-up
________ Subtask 21-51-51-410-057
 A. Close Access
 (1)
 Make sure that the work area is clean and clear of tool(s) and other items.
 (2)
 Close the access panels (Ref. TASK 53-35-13-400-002):
 (a)
 FOR 100HM
 191KB and 191BB.
 (b)
 FOR 101HM
 192KB and 192FB.
 Subtask 21-51-51-862-052
 B. De-energize the aircraft electrical circuits (Ref. TASK 24-41-00-862-002). 
R 1EFF : 051-099, 201-299, 301-302, 1 21-51-51Page 478 1 1 Aug 01/05 1 1 1CES 1
R  **ON A/C 106-149, 303-399, 401-499, 
 TASK 21-51-51-000-002-A 
 Removal of the Air Duct upstream of the Flow Control Unit 
 1. Reason for the Job__________________ 
 Self Explanatory 
 2. Job Set-up Information______________________ 
 A. Fixtures, Tools, Test and Support Equipment 
 -------------------------------------------------------------------------------REFERENCE QTY DESIGNATION ------------------------------------------------------------------------------- 
No specific No specific  circuit breaker(s) safety clip(s)protective covers 
 B. Referenced Information 
 -------------------------------------------------------------------------------REFERENCE DESIGNATION ------------------------------------------------------------------------------- 
21-51-51-200-002 24-41-00-861-002 53-35-13-000-002  Attachment Components (In-Service Wear Limits) - Air DuctEnergize the Aircraft Electrical Circuits from the External PowerRemoval of the Quick-Release Access Panels from the Belly Fairing Structure  
R  **ON A/C 106-149, 303-399,  
R  21-51-51-991-006  Fig. 403A  
R  **ON A/C 401-499, 
 21-51-51-991-006-A  Fig. 403B 
R 1EFF : 106-149, 303-399, 401-499, 1 21-51-51Page 479 1 1 Aug 01/05 1 1 1CES 1
 -------------------------------------------------------------------------------
REFERENCE DESIGNATION ------------------------------------------------------------------------------- 
R  **ON A/C 106-149, 303-399, 401-499, 
 21-51-51-991-008  Fig. 405A 
 3. Job Set-up__________ 
 Subtask 21-51-51-861-055 
 A. Energize the aircraft electrical circuits (Ref. TASK 24-41-00-861-002). 
 Subtask 21-51-51-865-066 
 B. Open, safety and tag this(these) circuit breaker(s): 
 -------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------FOR 23HB  
R  **ON A/C 401-499, 
R  49VU AIR COND/TEMP CTL/SYS 1 CHAN B/28VDC 122VU AIR COND/TEMP CTL SYS 1/CHAN A/115VAC 122VU AIR COND/TEMP CTL SYS 1/CHAN A/28VDC 122VU AIR COND/TEMP CTL SYS 1/CHAN B/115VAC  52HH 49HH 51HH 50HH  D08 X22X21Y18  
R  **ON A/C 106-149, 303-399, 401-499, 
 FOR 24HB  
R  **ON A/C 401-499, 
R R  122VU AIR COND/TEMP CTL SYS 2/CHAN A/115VAC 122VU AIR COND/TEMP CTL SYS 2/CHAN A/28VDC 122VU AIR COND/TEMP CTL SYS 2/CHAN B/28VDC 122VU AIR COND/TEMP CTL SYS 2/CHAN B/115VAC  53HH 55HH 56HH 54HH  W22W21 Y21Y20 
R 1EFF : 106-149, 303-399, 401-499, 1 21-51-51Page 480 1 1 Aug 01/05 1 1 1CES 1 中国航空网 www.aero.cn 航空翻译 www.aviation.cn 本文链接地址:A320飞机维护手册 AMM AIR CONDITIONING 空调 3(146)