(b)
Install the sense line connector (5).
(c)
TORQUE the sense line connector (5) to between 0.95 and 1.05 m.daN (84.07 and 92.92 lbf.in).
(20)
Remove the blanking caps from the electrical connectors.
(21)
Make sure that the electrical connectors are clean and in the correct condition.
(22) Connect the electrical connector (3). R **ON A/C 001-049, 101-105, 151-199,
Subtask 21-51-51-410-058-A
C. Installation of the Ozone Filter
(1) Install the ozone filter upstream of the flow control valve (Ref. TASK 21-51-41-400-001).
R 1EFF : 001-049, 055-099, 101-105, 151-199, 1 21-51-51Page 432 1201-210, 1May 01/05 1 1 1CES 1 Subtask 21-51-51-220-050-A
D. Post Installation Measurement and Adjustment
(1) Locations.
(a) At the sleeve (14): 1 Move the sleeve (14) until the Z dimensions are approximately
_
equal.
NOTE : Turn the sleeve when you move it.
____ This will help to prevent damage to the seals in the sleeve.
2 Do a check of the Y dimension:
_
-measure the maximum and minimum Y dimensions around the circumference of the sleeve (14),
-the difference between the maximum and minimum Y dimensions must not be more than 1.7 mm (0.0669 in.).
(b) At the mounting (21): 1 do a check of the dimension V between the mounting (21) and
_
the bracket (20).
-this dimension must not be less than 1.2 mm (0.0472 in.). NOTE : You can get these tolerances if you adjust:
____ - on the heat exchanger unit the tie-rod (1) and,
**ON A/C 001-003,
(Ref. Fig. 401/TASK 21-51-51-991-001-C) R **ON A/C 004-049, 101-105, 151-158,
(Ref. Fig. 401A/TASK 21-51-51-991-001) R **ON A/C 004-049, 101-105, 151-199, R Post SB 21-1134 For A/C 004-049,101-105,151-158,
(Ref. Fig. 401B/TASK 21-51-51-991-001-D)
R 1EFF : 001-049, 101-105, 151-199, 1 21-51-51Page 433 1 1 May 01/05 1 1 1CES 1
R **ON A/C 001-049, 101-105, 151-199,
- on the ozone filter the tie rod (1) (Ref. TASK 21-51-41-400-001). You must only adjust the tie-rods (1). Safety the tie-rods (1) after you adjust them.
(2) Make sure that the work area is clean and clear of tool(s) and other items.
R **ON A/C 051-099, 201-299, 301-302,
Subtask 21-51-51-410-058
C. Installation of the Air Duct upstream of the Flow Control Valve
(1) Install the air duct upstream of the flow control valve (Ref. TASK 21-51-51-400-002).
Subtask 21-51-51-220-050
D. Post Installation Measurement and Adjustment
(1) Locations.
(a) At the sleeve (14): 1 Move the sleeve (14) until the Z dimensions are approximately
_
equal.
NOTE : Turn the sleeve when you move it.
____ This will help to prevent damage to the seals in the sleeve.
2 Do a check of the Y dimension:
_
-measure the maximum and minimum Y dimensions around the circumference of the sleeve (14),
-the difference between the maximum and minimum Y dimensions must not be more than 1.7 mm (0.0669 in.).
(b) At the mounting (21): 1 do a check of the dimension V between the mounting (21) and
_
the bracket (20).
-this dimension must not be less than 1.2 mm (0.0472 in.).
R 1EFF : 001-049, 051-099, 101-105, 151-199, 1 21-51-51Page 434 1201-299, 301-302, 1May 01/05 1 1 1CES 1
R NOTE : You can get these tolerances if you adjust:____ - on the heat exchanger unit the tie-rod (1) and, **ON A/C 051-054,
R R (Ref. Fig. 401/TASK 21-51-51-991-001-C) **ON A/C 055-099, 201-209,
R R R (Ref. Fig. 401A/TASK 21-51-51-991-001) **ON A/C 055-099, 201-299, 301-302, Post SB 21-1134 For A/C 055-099,201-209, (Ref. Fig. 401B/TASK 21-51-51-991-001-D) **ON A/C 051-099, 201-299, 301-302,
R **ON A/C 051-054, - the tie rods (9).
R R (Ref. Fig. 403/TASK 21-51-51-991-006-B) **ON A/C 055-099, 201-299, 301-302,
R R (Ref. Fig. 403A/TASK 21-51-51-991-006) **ON A/C 051-099, 201-299, 301-302,
You must only adjust the tie-rods (1) and (9). Safety the tie-rods (1) and (9) after you adjust them.
(2) Make sure that the work area is clean and clear of tool(s) and other items.
R 1EFF : 051-099, 201-299, 301-302, 1 21-51-51Page 435 1 1 May 01/05 1 1 1CES 1
R Attachment Components - Air Duct
R Figure 403/TASK 21-51-51-991-006-B13 (SHEET 1)
R 1EFF : 051-054, 1 21-51-51Page 436 1 1 May 01/05 1 1 1CES 1
R Attachment Components - Air Duct
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM AIR CONDITIONING 空调 3(137)