R **ON A/C 062-099, 401-499,
49-12-52-991-001-A Fig. 401A
R **ON A/C 001-003, 051-099, 401-499,
3. Job Set-up
__________
Subtask 49-12-52-860-053
A. Aircraft Maintenance Configuration
(1)
Put the warning notices on panel 25VU to tell persons not to start the APU.
(2)
Energize the ground service network (Ref. TASK 24-41-00-861-002).
(3)
Make sure that the hydraulic systems are depressurized (Ref. TASK 29-00-00-864-001).
Subtask 49-12-52-865-050
B. Open, safety and tag this(these) circuit breaker(s):
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------121VU APU/APU/CTL 2KD L42 121VU APU/ECB/SPLY 1KD L41
Subtask 49-12-52-010-050
C. Get Access
(1)
Put the access platform below the access doors 315AL and 316AR.
(2)
Open the APU access doors 315AL, 316AR. (Ref. TASK 52-41-00-010-001)
(3)
Set the light switch 11LJ to on.
(4)
Remove the APU access doors 315AL, 316AR (Ref. TASK 52-41-21-000-001) (Ref. TASK 52-41-22-000-001).
4. Procedure
_________
**ON A/C 001-003, 051-061,
(Ref. Fig. 401/TASK 49-12-52-991-001) R **ON A/C 062-099, 401-499,
(Ref. Fig. 401A/TASK 49-12-52-991-001-A)
FWD RH Tie-Rods and Vibration Isolator
Figure 401/TASK 49-12-52-991-001
CES
FWD RH Tie-Rods and Vibration Isolator
Figure 401A/TASK 49-12-52-991-001-A
CES R **ON A/C 001-003, 051-099, 401-499,
Subtask 49-12-52-480-050
A. Installation of the HOIST- MINILIFT
WARNING : OBEY THE HOISTING SAFETY PROCEDURES.
_______ MAKE SURE THAT THE HOIST IS ASSEMBLED AND ATTACHED CORRECTLY BEFORE YOU PUT A LOAD ON IT. OBEY THE MANUFACTURER'S INSTRUCTIONS WHEN YOU USE THE HOIST. IF THE HOIST IS IN AN INCORRECT CONDITION THE LOAD CAN MOVE ACCIDENTALLY AND KILL PERSONS OR CAUSE INJURY.
CAUTION : DO NOT TURN THE HOIST HANDLE MORE THAN 90 DEGREES WHEN THE APU
_______ MOUNT BRACKETS ARE TIGHTLY ENGAGED ON THE VIBRATION ISOLATORS. IF YOU TURN THE HOIST HANDLE MORE THAN 90 DEGREES, YOU CAN CAUSE DAMAGE TO THE APU AND THE APU MOUNTS.
(1) Install the HOIST - MINILIFT (Ref. TASK 49-00-00-480-002)
**ON A/C 001-003, 051-061,
Subtask 49-12-52-020-050
B. Removal of the Vibration Isolator (40445KM)
(1)
Slowly wind the handle on the APU hoist until the APU hoist-cable is in tension.
(2)
Remove the nut (15) and install the PROTECTOR - THREADS, APU MOUNTING BOLTS on the cone bolt.
(3)
Remove and discard the cotter pins (3) and (11).
(4)
Remove the castle nuts (2)) and (13), the washers (1) and (12) and the bolts (5) and (17).
(5)
Remove the tie-rods (4) and (6) from the vibration isolator.
(6)
Remove the vibration isolator (4045KM) (16) from the APU mount-bracket (14).
(7)
If necessary remove the tie-rods (4) and/or (6).
(a)
Remove the nuts (9), the washers (8) and the screws (7).
(b)
Disconnect the bonding straps (10).
(c)
Remove and discard the cotter pins (21).
(d)
Remove the castle nuts (20), the washers (19) and the bolts (18).
(e) Remove the tie-rods (4) and/or (6). R **ON A/C 062-099, 401-499,
Subtask 49-12-52-020-050-A
B. Removal of the Vibration Isolator (4045KM)
(1)
Slowly wind the handle on the APU hoist until the APU hoist-cable is in tension.
(2)
Remove the nut (15) and install the PROTECTOR - THREADS, APU MOUNTING BOLTS on the cone bolt.
(3)
Remove and discard the cotter pins (3) and (11).
(4)
Remove the castle nuts (2)) and (13), the washers (1) and (12) and the bolts (5) and (17).