3. Job Set-up
__________
Subtask 52-13-11-860-050
A. Aircraft Maintenance Configuration
(1)
Make sure that the access platforms are in position.
(2)
Make sure that the special precautions are obeyed (Ref. TASK 52-10-00-860-001).
1EFF : ALL 1 52-13-11Page 413 1 1 Aug 01/05 1 1 1CES 1
(3)
Make sure that the drain holes in the door structure are not obstructed.
(4)
Make sure that the parts retained from the removed component are clean and in the correct condition.
Subtask 52-13-11-865-054
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged
-------------------------------------------------------------------------------PANEL DESIGNATION IDENT. LOCATION -------------------------------------------------------------------------------121VU EIS/SLIDES/ARM AND WARN/FLT 15WN P11 121VU EIS/SLIDES/ARM AND WARN/GND 13WN P10 121VU EIS/SDAC1 AND 2/DOOR/DET/PAX 48WV P05
Subtask 52-13-11-210-050
C. Check of the Rigging
**ON A/C 001-002,
(Ref. Fig. 404/TASK 52-13-11-991-007) R **ON A/C 003-049, 051-099, 101-149, 151-199, 201-299, 301-399, 401-499,
(Ref. Fig. 404A/TASK 52-13-11-991-007-A)
**ON A/C ALL
(1) Before you install the door, do a check with the rigging pins:
(a) Door in the up position: 1 With the RIGGING PIN (98DNSA20206120):
_
-rigging of the door lowering shaft (F).
-rigging of the compensation mechanism (K). 2 With the PIN - RIGGING (98D52103006000):
_
-rigging of the reducer shaft mechanism (H).
1EFF : ALL 1 52-13-11Page 414 1 1 Aug 01/05 1 1 1CES 1
Door Rigging
Figure 404/TASK 52-13-11-991-007
R 1EFF : 001-002, 1 52-13-11 Page 415
1 1 Feb 01/02
1 1
1CES 1
Door Rigging
Figure 404A/TASK 52-13-11-991-007-A
R 1EFF : 003-049, 051-099, 101-149, 151-199, 1 52-13-11Page 416 1201-299, 301-399, 401-499, 1Aug 01/05 1 1 1CES 1
(b) Door in the down position: 1 With the RIGGING PIN (98DNSA20206120):
_
-rigging of the triple lever of the percussion mechanism (V) (emergency control handle armed),
-
rigging of the emergency control handle (Pt). 2 With the PIN - RIGGING (98D52103006000):
_
-
rigging of the reducer shaft mechanism (H). 3 With the PIN - RIGGING (98D52103006000):
_
-rigging of the triple bellcrank on the locking shaft mechanism (E).
Subtask 52-13-11-081-050 R D. Removal of the Safety Barrier
(1) Remove the safety barrier installed in the opening of the removed door (Ref. TASK 52-00-00-081-001).
Subtask 52-13-11-420-054
E. Installation of the Eyebolt on the Door
(Ref. Fig. 402/TASK 52-13-11-991-004)
(1)
Put the eyebolt (26) on the door fitting with the washer (46) and the bush (45).
(2)
Install the flange (47).
(3)
Install the bolts (44) and the nuts (48).
(4)
Tighten the nuts (48).
(5)
Install the washer (43) and the nut (42).
(6)
Tighten the nut (42).
(7)
TORQUE the nut (42) to between 0.6 and 0.7 m.daN (53.09 and 61.94 lbf.in).
(8)
Install the cotter pin (56) (41)
1EFF : ALL 1 52-13-11Page 417 1 1 Feb 01/04 1 1 1CES 1 Subtask 52-13-11-010-054-A
F. Removal of the Lining Panels
(1)
Remove the frame lining flap (Ref. TASK 52-13-31-000-001).
(2)
Remove the frame lining panels.
(a)
For the left door (Ref. TASK 25-23-45-000-003): 261TW, 261UW, 261VW, 261WW.
(b)
For the right door (Ref. TASK 25-23-45-000-004): 262TW, 262UW, 262VW, 262WW.
Subtask 52-13-11-420-055
G. Installation of the Sling
(Ref. Fig. 401/TASK 52-13-11-991-002)
(1)
Remove the two self-adhesive patches (3) from the hoisting points. Discard the patches.
中国航空网 www.aero.cn
航空翻译 www.aviation.cn
本文链接地址:A320飞机维护手册 AMM DOORS 舱门2(79)